Project 18P00049

DPWH infrastructure contract
Contract ID:
18P00049
Fingerprint:
7ff3fa035aabde…af3e7ea12d Verified
Status:
Completed
Physical progress:
100%
Timeline:
Start Sep 17, 2018 (8 yrs 1 mo ago) · Target/actual end Jun 13, 2019
Description:
CONSTRUCTION/REHABILITATION OF ACCESSIBILITY FACILITIES FOR PHYSICALLY CHALLENGED PERSONS 1.HYDRO. #3, NANGALISAN, TUBA 2. PENGED, NANGALISAN, TUBA, 3. CAMP 6, DPWH-TOLLGATE, TUBA 4. CAMP 4 DPWH-FIELD CAMP, TUBA, 5. COLORADO FALLS, TWIN PEAKS, TUBA 6.TWIN
Category:
Buildings and Facilities
Implementing office:
DPWH Cordillera Administrative Region · Cordillera Administrative Region
Contractor:
CAD-ERA DESIGN AND BUILDER · DPWH contractor code 33076
Contract amount:
₱17,248,546.03 (₱17.2M)
Funding source:
Regular Infra - GAA 2018 Other Infrastructure (CSSP)
Budget year:
2018

Matching PhilGEPS award entries (same contractor, same contract ID)

RecordDateProcuring entityAmount
aa84bfb893bb…Aug 28, 2018DEPARTMENT OF PUBLIC WORKS AND HIGHWAYS - CAR₱18,438,477.90

Other DPWH contracts in the same city / municipality

View all
ContractStartDescriptionStatusAmount
25A00526Jun 16, 2025BASIC INFRASTRUCTURE PROGRAM (BIP), CONSTRUCTION OF FLOOD CONTROL STRUCTURE ALONG ARINGAY RIVER BASIN, BARANGAY SANTA CECILLA, ARINGAY, LA UNIONOn-Going₱67.2M
25AF0100Jun 11, 2025CONST/REHAB OF FLOOD MIT. FACI W/IN MAJOR RIVER BASINS & PRIN RIVERS - CONST. OF FLOOD MIT STRUCTURE ALONG ARINGAY RIVER BASIN, BRGY. POBLACION ARINGAY, LU (PHASE I)On-Going₱93.6M
25AF0101Jun 11, 2025CONST/REHAB OF FLOOD MIT. FACI W/IN MAJOR RIVER BASINS & PRINCIPAL RIVERS - CONST OF FLOOD MIT. STRUCTURE ALONG ARINGAY RIVER BASIN, BRGY. POBLACION ARINGAY, LU (PHASE 2)Completed₱93.6M
25AF0102Jun 11, 2025CONST/REHAB OF FLOOD MIT. FACI W/IN MAJOR RIVER BASINS & PRINCIPAL RIVERS - CONST. OF FLOOD MIT. STRUCTURE ALONG ARINGAY RIVER BASIN, BRGY. POBLACION, ARINGAY, LU (PHASE 3)Completed₱93.5M
25AF0103Jun 11, 2025CONST/REHAB. OF FLOOD MIT. FACI W/IN MAJOR RIVER BASINS & PRINCIPAL RIVERS - CONST. OF FLOOD MIT. STRUCTURE ALONG ARINGAY RIVER BASIN, BRGY. SAN JUAN WEST, ARINGAY, LA UNIONCompleted₱93.6M
25AF0104Jun 11, 2025CONST/REHAB OF FLOOD MIT. FACI W/IN MAJOR RIVER BASIN & PRINCIPAL RIVERS - CONST OF FOLOOD MIT. STRUCTURE ALONG ARINGAY, RIVER BASIN, BRGY. SAN SIMIN EAST, ARINGAY, LUOn-Going₱93.6M
25AF0105Jun 11, 2025CONST/REHAB OF FLOOD MIT FACI W/IN MAJOR RIVER BASINS & PRINCIPAL RIVERS - CONST. OF FLOOD MIT STRUCTURE ALONG ARINGAY RIVER BASIN, BRGY. SAN SIMON WEST, ARINGAY, LU (PHASE 1)On-Going₱93.6M
25AF0106Jun 11, 2025CONST/REHAB OF FLOOD MIT. FACI W/IN MAJOR RIVER BASINS & PRINCIPAL RIVERS - CONST. OF FLOOD MIT. STRUCTURE ALONG ARINGAY RIVER BASIN, BRGY. SAN SIMON WEST, ARINGAY, LU (PHASE 2)On-Going₱93.6M

Contract amounts as DPWH lists them, not payments. A contract alone does not establish irregularity.