Skip to content
FY2026 GAA: ₱6.79T
PisoScan

Project 19C00057

DPWH infrastructure contract
Contract ID:
19C00057
Fingerprint:
4c366c0e0c960d…1638a9fba7 Verified
Status:
Completed
Physical progress:
100%
Timeline:
Start Feb 28, 2020 (6 yrs 8 mo ago) · Target/actual end Aug 22, 2021
Description:
JICA-ASSISTED ROAD UPGRADING AND PRESERVATION PROJECT (RUPP) REHABILITATION/IMPROVEMENT ALONG DAANG MAHARLIKA, BULACAN, PROVINCE OF BULACAN
Category:
Roads
Implementing office:
Contract amount:
₱295,255,425.56 (₱295.3M)
Funding source:
Regular Infra - JICA PH P247 2019
Budget year:
2019

Other DPWH contracts in the same city / municipality

View all
ContractStartDescriptionStatusAmount
25C00491Jun 22, 2025NETWORK DEVELOPMENT PROGRAM-OFF-CARRIAGEWAY IMPROVEMENT-PRIMARY ROADS-MAHARLIKA HIGHWAY, PROVINCE OF BULACANOn-Going₱12.5M
25CC0280May 23, 2025CONSTRUCTION (COMPLETION) OF MULTI-PURPOSE BUILDING, BRGY. TIAONG, GUIGUINTO, BULACANOn-Going₱4.8M
25CC0303May 23, 2025CONSTRUCTION (COMPLETION) OF MULTI-PURPOSE BUILDING, BARANGAY SANTA CRUZ, GUIGUINTO, BULACANOn-Going₱19.3M
25CC0413May 23, 2025CONSTRUCTION OF ROAD INCLUDING DRAINAGE STRUCTURE, BARANGAY TABANG, GUIGUINTO, BULACANOn-Going₱4.9M
25CC0455May 23, 2025CONSTRUCTION OF MULTI-PURPOSE BUILDING TABANG ELEMENTARY SCHOOL, BARANGAY TABANG, GUIGUINTO, BULACANOn-Going₱47.8M
25CC0509May 23, 2025CONSTRUCTION OF MULTI-PURPOSE BUILDING (GUIGUINTO OVAL SPORTS COMPLEX) POBLACION, GUIGUINTO, BULACANOn-Going₱19.3M
24CC0669Mar 27, 2025CONSTRUCTION OF FLOOD CONTROL STRUCTURE AT BARANGAY MALIS (PUROK 4 TO PUROK 5), GUIGUINTO, BULACANOn-Going₱74.1M
25CC0325Mar 21, 2025CONSTRUCTION OF RIVERBANK PROTECTION STRUCTURE (PACKAGE A) AT BARANGAY SANTA CRUZ (PUROK 5), GUIGUINTO, BULACANOn-Going₱74.1M

Contract amounts as DPWH lists them, not payments. A contract alone does not establish irregularity.