Project 19C00090
DPWH infrastructure contract
Contract ID:
19C00090
Fingerprint:
202efd4e487b4b…a3c6b5de27 Verified
Status:
Completed
Physical progress:
100%
Timeline:
Start May 20, 2020 (6 yrs 5 mo ago) · Target/actual end Aug 6, 2020
Description:
CONSTRUCTION OF THE DENR-ENVIRONMENTAL MANAGEMENT BUREAU REGION III BUILDING (PHASE III), DIOSDADO MACAPAGAL GOVERNMENT CENTER, MAIMPIS, CITY OF SAN FERNANDO, PAMPANGA
Category:
Buildings and Facilities
Implementing office:
DPWH Region III · Region III
Contractor:
Contract amount:
₱3,922,973.86 (₱3.9M)
Funding source:
Outside Infra - Trust Funds 2019
Budget year:
2019
Matching PhilGEPS award entries (same contractor, same contract ID)
| Record | Date | Procuring entity | Amount |
|---|---|---|---|
| e780d6234d24… | Mar 16, 2020 | DEPARTMENT OF PUBLIC WORKS AND HIGHWAYS - REGION III | ₱3,922,973.86 |
Other DPWH contracts in the same city / municipality
View all| Contract | Start | Description | Status | Amount |
|---|---|---|---|---|
| 25CG0236 | Sep 4, 2025 | BASIC INFRASTRUCTURE PROGRAM (BIP): MULTI-PURPOSE BUILDINGS / FACILITIES TO SUPPORT SOCIAL SERVICES - COMPLETION OF MULTI PURPOSE BUILDINGS, DOLORES AND SAN JUAN, CITY OF SAN FERNANDO, PAMPANGA | Completed | ₱4.7M |
| 25CG0100 | Aug 5, 2025 | BASIC INFRASTRUCTURE PROGRAM (BIP): MULTI-PURPOSE BUILDINGS / FACILITIES TO SUPPORT SOCIAL SERVICES - CONSTRUCTION OF MULTI PURPOSE BUILDING, SAN PEDRO CUTUD, CITY OF SAN FERNANDO, PAMPANGA | Completed | ₱6.6M |
| 25CG0229 | Aug 5, 2025 | BASIC INFRASTRUCTURE PROGRAM (BIP): MULTI-PURPOSE BUILDINGS / FACILITIES TO SUPPORT SOCIAL SERVICES - COMPLETION OF MULTI PURPOSE BUILDING (COVERED COURT), DEL CARMEN (AFP-PNP) INTEGRATED SCHOOL, CITY OF SAN FERNANDO, PAMPANGA | Completed | ₱1.9M |
| 25CG0218 | Jul 29, 2025 | BASIC INFRASTRUCTURE PROGRAM (BIP): MULTI-PURPOSE BUILDINGS/ FACILITIES TO SUPPORT SOCIAL SERVICES - COMPLETION OF MULTI PURPOSE BUILDING, MALINO IS, CITY OF SAN FERNANDO, PAMPANGA | Completed | ₱1.9M |
| 25CG0239 | Jul 29, 2025 | BASIC INFRASTRUCTURE PROGRAM (BIP): MULTI-PURPOSE BUILDINGS / FACILITIES TO SUPPORT SOCIAL SERVICES - CONSTRUCTION OF MULTI PURPOSE BUILDING, SAN ISIDRO, CITY OF SAN FERNANDO, PAMPANGA | Completed | ₱6.6M |
| 25CG0084 | Jul 3, 2025 | BASIC INFRASTRUCTURE PROGRAM (BIP): ACCESS ROADS AND/OR BRIDGES FROM THE NATIONAL ROAD/S LEADING TO MAJOR/STRATEGIC PUBLIC BUILDINGS/FACILITIES - CONSTRUCTION OF ROAD, BRGY. CALIBUTBUT, BACOLOR, PAMPANGA | Completed | ₱9.4M |
| 25CG0090 | Jul 3, 2025 | BASIC INFRASTRUCTURE PROGRAM (BIP): ACCESS ROADS AND/OR BRIDGES FROM THE NATIONAL ROAD/S LEADING TO MAJOR/STRATEGIC PUBLIC BUILDINGS/FACILITIES - REHABILITATION/CONSTRUCTION OF ROADS, QUEBIAWAN, CITY OF SAN FERNANDO, PAMPANGA | Completed | ₱4.7M |
| 25CG0107 | Jul 3, 2025 | BASIC INFRASTRUCTURE PROGRAM (BIP): FLOOD MITIGATION STRUCTURES PROTECTING MAJOR/STRATEGIC PUBLIC BUILDINGS/FACILITIES - CONSTRUCTION OF DRAINAGE CANAL, BRGY CALIBUTBUT, BACOLOR, PAMPANGA | On-Going | ₱18.7M |
Contract amounts as DPWH lists them, not payments. A contract alone does not establish irregularity.