Project 19CC0094

DPWH infrastructure contract
Contract ID:
19CC0094
Fingerprint:
a0d8286b86d7b8…96fdfa0bf9 Verified
Status:
Completed
Physical progress:
100%
Timeline:
Start May 27, 2019 (7 yrs 5 mo ago) · Target/actual end Jul 25, 2019
Description:
CONSTRUCTION/IMPROVEMENT OF MULTI-PURPOSE BUILDING BRGY. POBLACION, GUIGUINTO, BULACAN
Category:
Buildings and Facilities
Implementing office:
DPWH Bulacan 1st DEO · Region III
Contractor:
JORENZ BUILDERS DEVELOPMENT CORP. · DPWH contractor code 41066
Contract amount:
₱966,335.29 (₱966.3K)
Funding source:
Regular Infra - GAA 2019 LP
Budget year:
2019

Other DPWH contracts in the same city / municipality

View all
ContractStartDescriptionStatusAmount
25C00491Jun 22, 2025NETWORK DEVELOPMENT PROGRAM-OFF-CARRIAGEWAY IMPROVEMENT-PRIMARY ROADS-MAHARLIKA HIGHWAY, PROVINCE OF BULACANOn-Going₱12.5M
25CC0280May 23, 2025CONSTRUCTION (COMPLETION) OF MULTI-PURPOSE BUILDING, BRGY. TIAONG, GUIGUINTO, BULACANOn-Going₱4.8M
25CC0303May 23, 2025CONSTRUCTION (COMPLETION) OF MULTI-PURPOSE BUILDING, BARANGAY SANTA CRUZ, GUIGUINTO, BULACANOn-Going₱19.3M
25CC0413May 23, 2025CONSTRUCTION OF ROAD INCLUDING DRAINAGE STRUCTURE, BARANGAY TABANG, GUIGUINTO, BULACANOn-Going₱4.9M
25CC0455May 23, 2025CONSTRUCTION OF MULTI-PURPOSE BUILDING TABANG ELEMENTARY SCHOOL, BARANGAY TABANG, GUIGUINTO, BULACANOn-Going₱47.8M
25CC0509May 23, 2025CONSTRUCTION OF MULTI-PURPOSE BUILDING (GUIGUINTO OVAL SPORTS COMPLEX) POBLACION, GUIGUINTO, BULACANOn-Going₱19.3M
24CC0669Mar 27, 2025CONSTRUCTION OF FLOOD CONTROL STRUCTURE AT BARANGAY MALIS (PUROK 4 TO PUROK 5), GUIGUINTO, BULACANOn-Going₱74.1M
25CC0325Mar 21, 2025CONSTRUCTION OF RIVERBANK PROTECTION STRUCTURE (PACKAGE A) AT BARANGAY SANTA CRUZ (PUROK 5), GUIGUINTO, BULACANOn-Going₱74.1M

Contract amounts as DPWH lists them, not payments. A contract alone does not establish irregularity.