Project 19CD0069
DPWH infrastructure contract
Contract ID:
19CD0069
Fingerprint:
b5cc447e28db97…b44881c84a Verified
Status:
Completed
Physical progress:
100%
Timeline:
Start Jul 11, 2019 (7 yrs 4 mo ago) · Target/actual end Dec 19, 2019
Description:
ASSET PRESERVATION REHABILITATION / RECONSTRUCTION OF NATIONAL ROADS WITH SLIPS, SLOPE COLLAPSE AND LANDSLIDE NORZAGARAY BIGTE ROAD, K0073 + 700 - K0074 + 100, NORZAGARAY, BULACAN
Category:
Roads
Implementing office:
DPWH Bulacan 2nd DEO · Region III
Contractor:
STO. CRISTO CONSTRUCTION & TRADING INC. (FOR: STO. CRISTO CONSTRUCTION & TRADING) · DPWH contractor code 26096
Contract amount:
₱18,580,074.67 (₱18.6M)
Funding source:
Regular Infra - GAA 2019 OO-1
Budget year:
2019
Matching PhilGEPS award entries (same contractor, same contract ID)
| Record | Date | Procuring entity | Amount |
|---|---|---|---|
| 6bf4b8c9f56f… | Jun 24, 2019 | DEPARTMENT OF PUBLIC WORKS AND HIGHWAYS - BULACAN 2ND DEO | ₱18,580,074.67 |
Other DPWH contracts in the same city / municipality
View all| Contract | Start | Description | Status | Amount |
|---|---|---|---|---|
| 25C00517 | Aug 18, 2025 | CONVERGENCE AND SPECIAL SUPPORT PROGRAM-BASIC INFRASTRUCTURE PROGRAM-ACCESS ROAD &/OR BRIDGES FR. THE NAT'L. RDS. LEADING TO MAJOR/STRATEGIC PUBLIC BLDGS./FACILITIES-CONSTRUCTION OF ROAD, BRGY, PARTIDA, NORZAGARAY, BULACAN, PROVINCE OF BULACAN | On-Going | ₱19.6M |
| 25CD0230 | Jun 26, 2025 | CONVERGENCE AND SPECIAL SUPPORT PROGRAM RAINWATER COLLECTOR SYSTEM | Completed | ₱2.5M |
| 25CD0149 | May 26, 2025 | COMPLETION OF ANGAT NEW MUNICIPAL HALL BUILDING, BARANGAY SAN ROQUE, ANGAT, BULACAN | On-Going | ₱48.0M |
| 25CD0156 | Apr 15, 2025 | CONSTRUCTION OF MULTI-PURPOSE BUILDING AT BARANGAY SAN MARTIN 2, SAN JOSE DEL MONTE, BULACAN | Completed | ₱4.8M |
| 25CD0158 | Apr 15, 2025 | CONSTRUCTION OF MULTI-PURPOSE BUILDING, BRGY. SAN MARTIN 1, SAN JOSE DEL MONTE, BULACAN | Completed | ₱4.9M |
| 25CD0159 | Apr 15, 2025 | CONSTRUCTION OF MULTI-PURPOSE BUILDING AT BARANGAY SAN MARTIN 3, SAN JOSE DEL MONTE, BULACAN | Completed | ₱4.9M |
| 25CD0160 | Apr 15, 2025 | CONSTRUCTION OF MULTI-PURPOSE BUILDING AT BARANGAY SAN MARTIN 4, SAN JOSE DEL MONTE, BULACAN | Completed | ₱4.9M |
| 25CD0162 | Apr 15, 2025 | CONSTRUCTION OF MULTI-PURPOSE BUILDING, BRGY. STA. CRUZ 4, SAN JOSE DEL MONTE, BULACAN | Completed | ₱4.8M |
Contract amounts as DPWH lists them, not payments. A contract alone does not establish irregularity.