Project 19CE0214

DPWH infrastructure contract
Contract ID:
19CE0214
Fingerprint:
3c462a1707a67f…e0b21c0676 Verified
Status:
Completed
Physical progress:
100%
Timeline:
Start Jun 28, 2019 (7 yrs 4 mo ago) · Target/actual end Sep 15, 2019
Description:
REHABILITATION OF FLOOD CONTROL STRUCTURES, BRGY. SAN EUSTACIO, ALIAGA, NUEVA ECIJA
Category:
Flood Control and Drainage
Implementing office:
Contractor:
SPECO BUILDERS INC. · DPWH contractor code 15301
As listed: SPECO BUILDERS INC. (FORMERLY VRF CONSTRUCTION)
Contract amount:
₱29,399,242.86 (₱29.4M)
Funding source:
Regular Infra - GAA 2019 OO-2
Budget year:
2019

Matching PhilGEPS award entries (same contractor, same contract ID)

RecordDateProcuring entityAmount
fa59795863cf…Jun 25, 2019DEPARTMENT OF PUBLIC WORKS AND HIGHWAYS - N. ECIJA 1ST DEO₱27,926,616.80

Other DPWH contracts in the same city / municipality

View all
ContractStartDescriptionStatusAmount
25CE0273Jul 7, 2025CONCRETING OF BRGY. SAN JUAN TO BRGY. UMANGAN FMR, ALIAGA, NUEVA ECIJACompleted₱29.5M
25CE0294Jul 1, 2025CONSTRUCTION OF FLOOD CONTROL STRUCTURE ALONG TALAVERA RIVER, BARANGAY STA. MONICA, ALIAGA, NUEVA ECIJACompleted₱72.1M
25CE0327Jun 9, 2025CONSTRUCTION (COMPLETION) OF MULTI-PURPOSE BUILDING, BARANGAY POBLACION WEST III, ALIAGA, NUEVA ECIJACompleted₱5.8M
25CE0282Jun 2, 2025CONSTRUCTION OF SCHOOL BUILDING, ALIAGA CENTRAL SCHOOL, BARANGAY POBLACION CENTRO, ALIAGA, NUEVA ECIJACompleted₱5.0M
25CE0297Jun 2, 2025CONSTRUCTION (COMPLETION) OF MULTI-PURPOSE BUILDING, BRGY. UMANGAN, ALIAGA, NUEVA ECIJACompleted₱3.9M
25CE0326Jun 2, 2025CONSTRUCTION (COMPLETION) OF MULTI-PURPOSE BUILDING, BRGY. POBLACION EAST II, ALIAGA, NUEVA ECIJACompleted₱3.0M
25CE0126Apr 2, 2025CONSTRUCTION OF ROAD, BARANGAY SAN JUAN, ALIAGA, NUEVA ECIJACompleted₱4.9M
25CE0189Apr 2, 2025CONSTRUCTION OF ROAD INCLUDING DRAINAGE STRUCTURE, BARANGAY BUCOT, ALIAGA, NUEVA ECIJACompleted₱4.9M

Contract amounts as DPWH lists them, not payments. A contract alone does not establish irregularity.