Project 19CE0254
DPWH infrastructure contract
Contract ID:
19CE0254
Fingerprint:
13b84e75439790…c797aec586 Verified
Status:
Completed
Physical progress:
100%
Timeline:
Start Sep 19, 2019 (7 yrs 2 mo ago) · Target/actual end Dec 17, 2019
Description:
CONSTRUCTION OF 1STY3CL, SAPANG CAWAYAN ES, SCIENCE CITY OF MUÑOZ, NUEVA ECIJA
Category:
Buildings and Facilities
Implementing office:
DPWH Nueva Ecija 1st DEO · Region III
Contractor:
ADROIT EJD CONSTRUCTION CORP. (FORMERLY: ADROIT CONSTRUCTION) · DPWH contractor code 11169
Contract amount:
₱5,510,934.33 (₱5.5M)
Funding source:
Outside Infra - GAA 2019 DepEd BEFF
Budget year:
2019
Other DPWH contracts in the same city / municipality
View all| Contract | Start | Description | Status | Amount |
|---|---|---|---|---|
| 25CE0355 | Dec 3, 2025 | CONSTRUCTION OF SCHOOL HEALTH FACILITIES, MUNOZ CS, SCIENCE CITY OF MUÑOZ, NUEVA ECIJA | Completed | ₱4.9M |
| 25CE0302 | Jul 30, 2025 | CONSTRUCTION OF CLASSROOM BUILDING AT CENTRAL LUZON STATE UNIVERSITY, MUNOZ, NUEVA ECIJA | Completed | ₱19.7M |
| 25CE0203 | Jul 9, 2025 | CONSTRUCTION OF MULTI-PURPOSE BUILDING, BARANGAY LICAONG, SCIENCE CITY OF MUÑOZ, NUEVA ECIJA | Completed | ₱5.9M |
| 25CE0204 | Jul 1, 2025 | CONSTRUCTION (COMPLETION) OF MULTI-PURPOSE BUILDING, MALIGAYA ES, BARANGAY MALIGAYA, SCIENCE CITY OF MUÑOZ, NUEVA ECIJA | Completed | ₱3.0M |
| 25CE0206 | Jul 1, 2025 | CONSTRUCTION OF MULTI-PURPOSE BUILDING, BARANGAY SAN FELIPE, SCIENCE CITY OF MUÑOZ, NUEVA ECIJA | Completed | ₱4.9M |
| 25CE0213 | Jul 1, 2025 | REPLACEMENT OF BOX CULVERT ALONG MUNOZ-TALUGTUG ROAD, BARANGAY CALISITAN, MUÑOZ, NUEVA ECIJA | Completed | ₱11.6M |
| 25CE0205 | Jun 30, 2025 | CONSTRUCTION OF MULTI-PURPOSE BUILDING, BARANGAY SAN ANTONIO, SCIENCE CITY OF MUÑOZ, NUEVA ECIJA | Completed | ₱5.9M |
| 25CE0218 | Jun 30, 2025 | CONSTRUCTION OF WATER SYSTEM, BARANGAY VILLA ISLA, SCIENCE CITY OF MUÑOZ, NUEVA ECIJA | On-Going | ₱4.4M |
Contract amounts as DPWH lists them, not payments. A contract alone does not establish irregularity.