Skip to content
FY2026 GAA: ₱6.79T
PisoScan

Project 19CG0062

DPWH infrastructure contract
Contract ID:
19CG0062
Fingerprint:
607bb2ca2b9c66…63288b0322 Verified
Status:
Completed
Physical progress:
100%
Timeline:
Start Sep 27, 2019 (7 yrs 1 mo ago) · Target/actual end Nov 25, 2019
Description:
REHABILITATION/ REPAIR/IMPROVEMENT OF MULTI - PURPOSE BUILDING (STA. LUCIA ANAC DAY CARE CENTER) BARANGAY STA. LUCIA ANAC, MASANTOL, PAMPANGA
Category:
Buildings and Facilities
Implementing office:
DPWH Pampanga 1st DEO · Region III
Contractor:
MARVERIC BUILDERS · DPWH contractor code 17102
Contract amount:
₱1,411,176.87 (₱1.4M)
Funding source:
Regular Infra - GAA 2019 LP
Budget year:
2019

Matching PhilGEPS award entries (same contractor, same contract ID)

RecordDateProcuring entityAmount
7d5a27f787bc…Sep 16, 2019DEPARTMENT OF PUBLIC WORKS AND HIGHWAYS - PAMPANGA 1ST DEO₱1,411,176.87

Other DPWH contracts in the same city / municipality

View all
ContractStartDescriptionStatusAmount
25CG0176Jun 24, 2025CONCRETING OF CADUANG TETE TO BRGY. SAPLAD DAVID FARM-TO-MARKET ROAD, BRGY. CADUANG TETE AND BRGY. SAPLAD DAVID, MACABEBE PAMPANGACompleted₱4.7M
25CG0087May 22, 2025BASIC INFRASTRUCTURE PROGRAM (BIP): ACCESS ROADS AND/OR BRIDGES FROM THE NATIONAL ROAD/S LEADING TO MAJOR/STRATEGIC PUBLIC BUILDINGS/FACILITIES - CONSTRUCTION OF ROAD WITH SLOPE PROTECTION WORKS, SITIO PENA, BARANGAY SUA, MASANTOL, PAMPANGACompleted₱93.8M
25CG0088May 22, 2025SUSTAINABLE INFRASTRUCTURE PROJECTS ALLEVIATING GAPS (SIPAG): FLOOD MITIGATION STRUCTURES PROTECTING MAJOR / STRATEGIC PUBLIC BUIDLINGS / FACULTIES - REHABILITATION OF FLOOD CONTROL STRUCTURE ALONG PAMPANGA RIVER (PHASE I) AT BARANGAY CONSUELO, MACABEBE,On-Going₱140.3M
25CC0297Mar 21, 2025CONSTRUCTION OF REVETMENT AT BARANGAY SANTA LUCIA, CALUMPIT, BULACANOn-Going₱37.7M
25CG0025Feb 28, 2025FLOOD MANAGEMENT PROGRAM: CONSTRUCTION/ REHABILITATION OF FLOOD MITIGATION FACILITIES WITHIN MAJOR RIVER BASINS AND PRINCIPAL RIVERS - CONSTRUCTION OF FLOOD CONTROL STRUCTURE ALONG PAMPANGA RIVER, (DOWNSTREAM- RIGHT BANK) BARANGAY CONSUELO, MACABEBE, PAMPCompleted₱46.5M
25CG0029Feb 21, 2025FLOOD MANAGEMENT PROGRAM: CONSTRUCTION/ REHABILITATION OF FLOOD MITIGATION FACILITIES WITHIN MAJOR RIVER BASINS AND PRINCIPAL RIVERS - REHABILITATION OF ERODED PROTECTION DIKE ALONG PAMPANGA RIVER, BARANGAY CONSUELO, MACABEBE, PAMPANGAOn-Going₱93.2M
25CC0123Feb 10, 2025REHABILITATION OF ROAD, BARANGAY MEYTO, CALUMPIT, BULACANCompleted₱9.7M
24CG0308Sep 13, 2024BASIC INFRASTRUCTURE PROGRAM (BIP): MULTI-PURPOSE BUILDINGS/ FACILITIES TO SUPPORT SOCIAL SERVICES - CONSTRUCTION/ REHABILITATION OF MULTI-PURPOSE BUILDING, MACABEBE, PAMPANGACompleted₱9.4M

Contract amounts as DPWH lists them, not payments. A contract alone does not establish irregularity.