Project 19CH0025

DPWH infrastructure contract
Contract ID:
19CH0025
Fingerprint:
848b97f046872a…9d1a0570bc Verified
Status:
Completed
Physical progress:
100%
Timeline:
Start Jun 12, 2019 (7 yrs 5 mo ago) · Target/actual end Jul 11, 2019
Description:
CONCRETING OF ROAD, BRGY. STA. LUCIA, SASMUAN, PAMPANGA
Category:
Roads
Implementing office:
DPWH Pampanga 2nd DEO · Region III
Contractor:
ESN CONSTRUCTION & TRADING · DPWH contractor code 32720
Contract amount:
₱1,898,039.84 (₱1.9M)
Funding source:
Regular Infra - GAA 2019 LP
Budget year:
2019

Matching PhilGEPS award entries (same contractor, same contract ID)

RecordDateProcuring entityAmount
3150b5d2cf5c…May 21, 2019DEPARTMENT OF PUBLIC WORKS AND HIGHWAYS - PAMPANGA 2ND DEO₱1,898,039.84

Other DPWH contracts in the same city / municipality

View all
ContractStartDescriptionStatusAmount
25CH0039Apr 3, 2025CONSTRUCTION OF SLOPE PROTECTION STRUCTURE, BARANGAY SAN PEDRO, SASMUAN, PAMPANGA, PHASE 1, SASMUAN, PAMPANGACompleted₱29.7M
25CH0024Feb 24, 2025CONSTRUCTION OF FLOOD CONTROL STRUCTURE AT SANTA MONICA, SASMUAN, PAMPANGACompleted₱29.4M
25CH0030Feb 24, 2025CONSTRUCTION OF SLOPE PROTECTION STRUCTURE, BARANGAY BATANG 2ND, SASMUAN, PAMPANGACompleted₱29.7M
25CH0031Feb 24, 2025CONSTRUCTION OF SLOPE PROTECTION STRUCTURE, BARANGAY BATANG 2ND, SASMUAN, PAMPANGA, PHASE 2, SASMUAN, PAMPANGACompleted₱29.4M
25CH0032Feb 24, 2025CONSTRUCTION OF SLOPE PROTECTION STRUCTURE BARANGAY SABITANAN, SASMUAN, PAMPANGAOn-Going₱29.4M
24CH0122Jun 13, 2024CONSTRUCTION OF MULTI-PURPOSE BUILDING BARANGAY STA. MONICA, SASMUAN, PAMPANGACompleted₱4.9M
23CH0078Jun 14, 2023CONSTRUCTION OF MULTI-PURPOSE BUILDING, BARANGAY SAN PEDRO, SASMUAN, PAMPANGACompleted₱4.9M
23CH0062Apr 24, 2023REHABILITATION OF SLOPE PROTECTION ALONG UPPER DALAN BAPOR, PHASE II, AT SASMUAN, PAMPANGACompleted₱96.5M

Contract amounts as DPWH lists them, not payments. A contract alone does not establish irregularity.