Skip to content
FY2026 GAA: ₱6.79T
PisoScan

Project 19CJ0069

DPWH infrastructure contract
Contract ID:
19CJ0069
Fingerprint:
853712a4e3b379…8c153f13b0 Verified
Status:
Completed
Physical progress:
100%
Timeline:
Start Jul 5, 2019 (7 yrs 4 mo ago) · Target/actual end Oct 31, 2019
Description:
ASSET PRESERVATION PROGRAM REHABILITATION/ RECONSTRUCTION OF NATIONAL ROADS WITH SLIPS, SLOPE COLLAPSE, AND LANDSLIDE CAPAS-SAN JOSE-MAYANTOC-MALACAMPA RD - K0121 + (-357.00) - K0121 + (-187.00)
Category:
Roads
Implementing office:
DPWH Tarlac DEO · Region III
Contractor:
Contract amount:
₱13,964,769.82 (₱14.0M)
Funding source:
Regular Infra - GAA 2019 OO-1
Budget year:
2019

Other DPWH contracts in the same city / municipality

View all
ContractStartDescriptionStatusAmount
25CC0469May 23, 2025CONSTRUCTION OF MULTI-PURPOSE BUILDING BARANGAY MALAWAK, BUSTOS, BULACANOn-Going₱18.3M
25CC0470May 23, 2025CONSTRUCTION (COMPLETION) OF MULTI-PURPOSE FACILITY (SPORTS COMPLEX), POBLACION, BUSTOS, BULACANOn-Going₱29.0M
25CC0492May 23, 2025CONSTRUCTION OF ROAD AT BARANGAY TALAMPAS , BUSTOS, BULACANOn-Going₱47.6M
25CC0534May 23, 2025CONSTRUCTION OF MULTI-PURPOSE BUILDING, BARANGAY TANAWAN, BUSTOS, BULACANOn-Going₱19.3M
25CD0219Apr 15, 2025IMPROVEMENT OF NORZAGARAY-ANGAT-BUSTOS DIVERSION ROAD IN NORZAGARAY AND ANGAT, BULACANOn-Going₱4.8M
25CC0210Apr 8, 2025CONSTRUCTION OF ROAD AT BARANGAY LICIADA, BUSTOS, BULACANOn-Going₱9.4M
25CC0393Apr 8, 2025CONSTRUCTION (COMPLETION) OF MULTI-PURPOSE BUILDING, BUSTOS, BULACANOn-Going₱14.5M
25CC0504Apr 4, 2025REHABILITATION OF BRIDGE, PUROK 7, BARANGAY BONGA MAYOR, BUSTOS, BULACANOn-Going₱4.9M

Contract amounts as DPWH lists them, not payments. A contract alone does not establish irregularity.