Project 19CL0033
DPWH infrastructure contract
Contract ID:
19CL0033
Fingerprint:
1d76482ee8438a…a3257b844b Verified
Status:
Completed
Physical progress:
100%
Timeline:
Start Aug 28, 2019 (7 yrs 2 mo ago) · Target/actual end Nov 25, 2019
Description:
CONSTRUCTION OF MULTI-PURPOSE BUILDING (COVERED COURT) BARANGAY LUCAPON SOUTH, STA. CRUZ, ZAMBALES
Category:
Buildings and Facilities
Implementing office:
DPWH Zambales 1st DEO · Region III
Contractor:
JECK CONSTRUCTION · DPWH contractor code 24189
Contract amount:
₱4,850,851.91 (₱4.9M)
Funding source:
Regular Infra - GAA 2019 LP
Budget year:
2019
Matching PhilGEPS award entries (same contractor, same contract ID)
| Record | Date | Procuring entity | Amount |
|---|---|---|---|
| a2d80e6faee4… | Jun 27, 2019 | DEPARTMENT OF PUBLIC WORKS AND HIGHWAYS - ZAMBALES 1ST DEO | ₱4,850,851.91 |
Other DPWH contracts in the same city / municipality
View all| Contract | Start | Description | Status | Amount |
|---|---|---|---|---|
| 25CL0101 | Jul 7, 2025 | CONSTRUCTION OF MULTI-PURPOSE BUILDING, BRGY. GUINABON, STA CRUZ, ZAMBALES | On-Going | ₱17.6M |
| 25CL0105 | Jul 7, 2025 | COMPLETION OF MULTI-PURPOSE BUILDING, BRGY. SOUTH POBLACION, STA. CRUZ, ZAMBALES | On-Going | ₱13.7M |
| 25CL0199 | Jul 7, 2025 | CONSTRUCTION OF MULTI-PURPOSE BUILDING, SITIO ACOJE, BRGY. LUCAPON SOUTH, STA. CRUZ, ZAMBALES | On-Going | ₱16.6M |
| 25CL0206 | Jul 7, 2025 | CONSTRUCTION OF WATER SYSTEM, BRGY. LUCAPON SOUTH, STA. CRUZ, ZAMBALES | On-Going | ₱9.9M |
| 25CL0222 | May 28, 2025 | CONSTRUCTION OF WATER SUPPLY SYSTEM, BARANGAY BOLITOC, SANTA CRUZ, ZAMBALES | On-Going | ₱9.9M |
| 25CL0226 | May 23, 2025 | CONSTRUCTION OF ACCESS ROAD/ DIVERSION ROAD INCLUDING DRAINAGE STRUCTURE, DAAN KALIKASAN TO UACON, PHASE 2, SANTA CRUZ, ZAMBALES | On-Going | ₱95.3M |
| 25CL0227 | May 23, 2025 | CONSTRUCTION OF ACCESS ROAD/ DIVERSION ROAD INCLUDING DRAINAGE STRUCTURE, DAAN KALIKASAN TO UACON, PHASE 3, SANTA CRUZ, ZAMBALES | On-Going | ₱95.3M |
| 25CL0077 | Apr 3, 2025 | CONSTRUCTION OF RIVERBANK PROTECTION STRUCTURE ALONG BAYTO RIVER, PHASE 10, SANTA CRUZ, ZAMBALES | On-Going | ₱96.5M |
Contract amounts as DPWH lists them, not payments. A contract alone does not establish irregularity.