Project 19DC0065
DPWH infrastructure contract
Contract ID:
19DC0065
Fingerprint:
c0d610e831c4f7…6fdd28b647 Verified
Status:
Completed
Physical progress:
100%
Timeline:
Start May 24, 2019 (7 yrs 5 mo ago) · Target/actual end Jul 7, 2019
Description:
LOCAL PROGRAM, LOCAL INFRASTRUCTURE PROGRAM, WATER MANAGEMENT FACILITIES, WATER SUPPLY, REPAIR/REHAB/IMPROVEMENT OF WATER SUPPLY-LEVEL II, BRGY. PANSIPIT, AGONCILLO, BATANGAS
Category:
Water Provision and Storage
Implementing office:
DPWH Batangas 3rd DEO · Region IV-A
Contractor:
OIC CONZTRUCT AND SUPPLY CORPORATION(FORMERLY:OIC CONST.) · DPWH contractor code 23727
Contract amount:
₱950,444.67 (₱950.4K)
Funding source:
Regular Infra - GAA 2019 LP
Budget year:
2019
Matching PhilGEPS award entries (same contractor, same contract ID)
| Record | Date | Procuring entity | Amount |
|---|---|---|---|
| 76d04f3f7d83… | May 14, 2019 | DEPARTMENT OF PUBLIC WORKS AND HIGHWAYS - BATANGAS 3RD ED | ₱950,444.67 |
Other DPWH contracts in the same city / municipality
View all| Contract | Start | Description | Status | Amount |
|---|---|---|---|---|
| 25DC0092 | Jun 2, 2025 | CONVERGENCE AND SPECIAL SUPPORT PROGRAM, BASIC INFRASTRUCTURE PROGRAM (BIP), BIP - ACCESS ROADS AND/OR BRIDGES FROM THE NATIONAL ROAD/S LEADING TO MAJOR/STRATEGIC PUBLIC BUILDINGS/FACILITIES, REHABILITATION OF BRIDGE, BARANGAY CORAL NA MUNTI, AGONCILLO, B | Completed | ₱4.9M |
| 25DC0122 | Jun 2, 2025 | CONVERGENCE AND SPECIAL SUPPORT PROGRAM, BASIC INFRASTRUCTURE PROGRAM (BIP), BIP - MULTI-PURPOSE BUILDINGS/FACILITIES TO SUPPORT SOCIAL SERVICES, REHABILITATION OF THE PNP BUILDING, AGONCILLO, BATANGAS | Completed | ₱4.9M |
| 25DC0152 | Jun 2, 2025 | CONVERGENCE AND SPECIAL SUPPORT PROGRAM, BASIC INFRASTRUCTURE PROGRAM (BIP), BIP - ACCESS ROADS AND/OR BRIDGES FROM NATIONAL ROAD/S LEADING TO MAJOR/STRATEGIC PUBLIC BUILDINGS/FACILITIES, REHABILITATION OF BRIDGE INCLUDING APPROACHES AT BARANGAY ADIA, AGO | Completed | ₱9.9M |
| 25DC0098 | May 29, 2025 | CONVERGENCE AND SPECIAL SUPPORT PROGRAM, SUSTAINABLE INFRASTRUCTURE PROJECTS ALLEVIATING GAPS (SIPAG), SIPAG-ACCESS ROADS AND/OR BRIDGES FROM THE NATIONAL ROAD/S LEADING TO MAJOR/STRATEGIC PUBLIC BUILDINGS/FACILITIES, CONSTRUCTION OF ROAD AT BARANGAY BANG | On-Going | ₱14.3M |
| 25DC0107 | May 29, 2025 | CONVERGENCE AND SPECIAL SUPPORT PROGRAM, BASIC INFRASTRUCTURE PROGRAM (BIP), BIP - ACCESS ROADS AND/OR BRIDGES FROM THE NATIONAL ROADS LEADING TO MAJOR/STRATEGIC PUBLIC BUILDINGS/FACILITIES, REHABILITATION OF ROADS ALONG SAN JACINTO-BARRIGON, AGONCILLO, B | On-Going | ₱14.8M |
| 25DC0108 | May 29, 2025 | CONVERGENCE AND SPECIAL SUPPORT PROGRAM, BASIC INFRASTRUCTURE PROGRAM (BIP), BIP - ACCESS ROADS AND/OR BRIDGES FROM THE NATIONAL ROADS LEADING TO MAJOR/STRATEGIC PUBLIC BUILDINGS/FACILITIES, REHABILITATION OF ROADS AT BARANGAY BANYAGA, AGONCILLO, BATANGAS | On-Going | ₱14.5M |
| 25DC0111 | May 29, 2025 | CONVERGENCE AND SPECIAL SUPPORT PROGRAM, BASIC INFRASTRUCTURE PROGRAM (BIP), BIP - ACCESS ROADS AND/OR BRIDGES FROM THE NATIONAL ROADS LEADING TO MAJOR/STRATEGIC PUBLIC BUILDINGS/FACILITIES, REHABILITATION OF ROADS AT BARANGAY BILIBINWANG, AGONCILLO, BATA | On-Going | ₱14.8M |
| 25DC0118 | May 21, 2025 | CONVERGENCE AND SPECIAL SUPPPORT PROGRAM, BIP-MULTI PURPOSE BUILDINGS/FACILITIES TO SUPPORT SOCIAL SERVICES, BASIC INFRASTRUCTURE PROGRAM (BIP), IMPROVEMENT OF MULTI-PURPOSE BUILDING AT BARANGAY SUBIC ILAYA, AGONCILLO, BATANGAS | On-Going | ₱4.8M |
Contract amounts as DPWH lists them, not payments. A contract alone does not establish irregularity.