Project 19DD0201
DPWH infrastructure contract
Contract ID:
19DD0201
Fingerprint:
9119a9033fe6f2…a7021091e0 Verified
Status:
Completed
Physical progress:
100%
Timeline:
Start Jul 22, 2019 (7 yrs 3 mo ago) · Target/actual end Aug 20, 2019
Description:
LOCAL PROGRAM, BUILDINGS AND OTHER STRUCTURES - MULTIPURPOSE/ FACILITIES/ LOCAL INFRASTRUCTURE PROGRAM, IMPROVEMENT OF MULTI-PURPOSE BUILDING IN PAL-SICO ES, BRGY. SICO 2, SAN JUAN, BATANGAS
Category:
Buildings and Facilities
Implementing office:
DPWH Batangas 4th DEO · Region IV-A
Contractor:
IKM BUILDERS AND CONSTRUCTION SUPPLY CORPORATION · DPWH contractor code 30252
As listed: IKM BUILDERS AND CONSTRUCTION SUPPLY CORPORATION (FORMERLY: IKM BUILDERS & CONSTRUCTION SUPPLY)
Contract amount:
₱1,440,450.00 (₱1.4M)
Funding source:
Regular Infra - GAA 2019 LP
Budget year:
2019
Other DPWH contracts in the same city / municipality
View all| Contract | Start | Description | Status | Amount |
|---|---|---|---|---|
| 25D00017 | May 21, 2025 | CONSTRUCTION OF BY-PASS AND DIVERSION ROADSSAN JUAN BYPASS (ROSARIO-SAN JUAN-LAIYA TOURISM BYPASS ROAD) CANDELARIA-SAN JUAN-ROSARIO, PACKAGE 4, SAN JUAN BATANGAS | On-Going | ₱89.4M |
| 25D00018 | Apr 10, 2025 | CONSTRUCTION OF REVETMENT ALONG MALAKING ILOG RIVER, PHASE 1, BARANGAY MARAYKIT, SAN JUAN, BATANGAS | On-Going | ₱94.1M |
| 25D00027 | Apr 10, 2025 | WIDENING OF PERMANENT BRIDGES BANTILAN BR. (B02946LZ) ALONG SN JUAN-CANDELARIA JCT-CANDELARIA-BOLBOC RD | On-Going | ₱34.7M |
| 25D00128 | Apr 10, 2025 | CONSTRUCTION OF FLOOD MITIGATION STRUCTURE ALONG MALAKING TUBIG RIVER, PHASE 3, TIAONG, QUEZON | On-Going | ₱95.1M |
| 25D00016 | Apr 4, 2025 | CONSTRUCTION OF BY-PASS AND DIVERSION ROADS SAN JUAN BYPASS (ROSARIO-SAN JUAN-LAIYA TOURISM BYPASS ROAD) CANDELARIA-SAN JUAN-ROSARIO, PACKAGE 3, SAN JUAN BATANGAS | On-Going | ₱230.5M |
| 25D00054 | Apr 4, 2025 | CONSTRUCTION OF BY-PASS AND DIVERSION ROADS SAN JUAN BYPASS (ROSARIO-SAN JUAN-LAIYA TOURISM BYPASS ROAD), BATANGAS | On-Going | ₱47.0M |
| 24DD0300 | Mar 27, 2025 | CONCRETING OF BARANGAY PULANGBATO FMR, BARANGAY PULANGBATO, SAN JUAN, BATANGAS | On-Going | ₱19.3M |
| 24DD0303 | Mar 27, 2025 | CONCRETING OF BARANGAY SAMPIRO FMR, BARANGAY SAMPIRO, SAN JUAN, BATANGAS | On-Going | ₱14.5M |
Contract amounts as DPWH lists them, not payments. A contract alone does not establish irregularity.