Project 19DD0266
DPWH infrastructure contract
Contract ID:
19DD0266
Fingerprint:
d1a5e438a80d1b…f1c01331fa Verified
Status:
Completed
Physical progress:
100%
Timeline:
Start Jun 13, 2019 (7 yrs 5 mo ago) · Target/actual end Jun 3, 2020
Description:
ORGANIZATIONAL OUTCOME 2: PROTECT LIVES AND PROPERTIES AGAINST MAJOR FLOODS, FLOOD MANAGEMENT PROGRAM- CONSTRUCTION/ MAINTENANCE OF FLOOD MITIGATION STRUCTURES AND DRAINAGE SYSTEMS, CONSTRUCTION/ RESTORATION OF SLOPE PROTECTION/REVETMENT ALONG LAWAYE RIVE
Category:
Flood Control and Drainage
Implementing office:
DPWH Batangas 4th DEO · Region IV-A
Contractor:
W. RIVERA CONST. AND EQUIPT. RENTALS, INC. (FORMERLY: W. RIVERA CONSTRUCTION & EQUIPMENT RENTALS) · DPWH contractor code 31378
Contract amount:
₱23,765,000.00 (₱23.8M)
Funding source:
Regular Infra - GAA 2019 OO-2
Budget year:
2019
Other DPWH contracts in the same city / municipality
View all| Contract | Start | Description | Status | Amount |
|---|---|---|---|---|
| 25D00017 | May 21, 2025 | CONSTRUCTION OF BY-PASS AND DIVERSION ROADSSAN JUAN BYPASS (ROSARIO-SAN JUAN-LAIYA TOURISM BYPASS ROAD) CANDELARIA-SAN JUAN-ROSARIO, PACKAGE 4, SAN JUAN BATANGAS | On-Going | ₱89.4M |
| 25D00018 | Apr 10, 2025 | CONSTRUCTION OF REVETMENT ALONG MALAKING ILOG RIVER, PHASE 1, BARANGAY MARAYKIT, SAN JUAN, BATANGAS | On-Going | ₱94.1M |
| 25D00027 | Apr 10, 2025 | WIDENING OF PERMANENT BRIDGES BANTILAN BR. (B02946LZ) ALONG SN JUAN-CANDELARIA JCT-CANDELARIA-BOLBOC RD | On-Going | ₱34.7M |
| 25D00128 | Apr 10, 2025 | CONSTRUCTION OF FLOOD MITIGATION STRUCTURE ALONG MALAKING TUBIG RIVER, PHASE 3, TIAONG, QUEZON | On-Going | ₱95.1M |
| 25D00016 | Apr 4, 2025 | CONSTRUCTION OF BY-PASS AND DIVERSION ROADS SAN JUAN BYPASS (ROSARIO-SAN JUAN-LAIYA TOURISM BYPASS ROAD) CANDELARIA-SAN JUAN-ROSARIO, PACKAGE 3, SAN JUAN BATANGAS | On-Going | ₱230.5M |
| 25D00054 | Apr 4, 2025 | CONSTRUCTION OF BY-PASS AND DIVERSION ROADS SAN JUAN BYPASS (ROSARIO-SAN JUAN-LAIYA TOURISM BYPASS ROAD), BATANGAS | On-Going | ₱47.0M |
| 24DD0300 | Mar 27, 2025 | CONCRETING OF BARANGAY PULANGBATO FMR, BARANGAY PULANGBATO, SAN JUAN, BATANGAS | On-Going | ₱19.3M |
| 24DD0303 | Mar 27, 2025 | CONCRETING OF BARANGAY SAMPIRO FMR, BARANGAY SAMPIRO, SAN JUAN, BATANGAS | On-Going | ₱14.5M |
Contract amounts as DPWH lists them, not payments. A contract alone does not establish irregularity.