Skip to content
FY2026 GAA: ₱6.79T
PisoScan

Project 19DE0072

DPWH infrastructure contract
Contract ID:
19DE0072
Fingerprint:
b7b5683c36fc61…78acc0668a Verified
Status:
Completed
Physical progress:
100%
Timeline:
Start Jul 15, 2019 (7 yrs 4 mo ago) · Target/actual end Sep 28, 2019
Description:
LOCAL INFRASTRUCTURE PROGRAM - CONSTRUCTION/REPAIR/REHABILITATION/IMPROVEMENT OF MULTI-PURPOSE BUILDING, SAN LUIS, BATANGAS
Category:
Buildings and Facilities
Implementing office:
DPWH Batangas 2nd DEO · Region IV-A
Contractor:
RBG CONSTRUCTION SERVICES · DPWH contractor code 41725
Contract amount:
₱1,979,979.37 (₱2.0M)
Funding source:
Regular Infra - GAA 2019 LP
Budget year:
2019

Matching PhilGEPS award entries (same contractor, same contract ID)

RecordDateProcuring entityAmount
3f639f7f3282…Jul 3, 2019DEPARTMENT OF PUBLIC WORKS AND HIGHWAYS - BATANGAS 2ND ED₱1,940,792.17

Other DPWH contracts in the same city / municipality

View all
ContractStartDescriptionStatusAmount
25DE0182Jun 9, 2025CONVERGENCE AND SPECIAL SUPPORT PROGRAM, BASIC INFRASTRUCTURE PROGRAM (BIP), PUBLIC WATER SUPPLY SYSTEM, CONSTRUCTION (COMPLETION) OF WATER SYSTEM INCLUDING GENERATOR SET AT BARANGAY LOCLOC, SAN LUIS, BATANGASCompleted₱4.8M
25DE0079May 26, 2025CONVERGENCE AND SPECIAL SUPPORT PROGRAM, BASIC INFRASTRUCTURE PROGRAM (BIP), PUBLIC WATER SUPPLY SYSTEM, CONSTRUCTION OF WATER SUPPLY SYSTEM (WATER WORKS), BARANGAY ABIACAO, SAN LUIS, BATANGASOn-Going₱4.8M
25DE0089May 26, 2025CONVERGENCE AND SPECIAL SUPPORT PROGRAM, BASIC INFRASTRUCTURE PROGRAM (BIP), MULTI-PURPOSE BUILDINGS/FACILITIES TO SUPPORT SOCIAL SERVICES, CONSTRUCTION/REHABILITATION OF MULTI-PURPOSE BUILDING (COVERED COURT) SAN MARTIN, SAN LUIS BATANGASCompleted₱4.8M
25DE0125May 26, 2025CONVERGENCE AND SPECIAL SUPPORT PROGRAM, BASIC INFRASTRUCTURE PROGRAM (BIP), MULTI-PURPOSE BUILDINGS/FACILITIES TO SUPPORT SOCIAL SERVICES, CONSTRUCTION (COMPLETION) OF MULTI-PURPOSE BUILDING (COVERED COURT) AT BRGY. TUNGAL, SAN LUIS, BATANGASCompleted₱9.6M
25DE0128May 26, 2025CONVERGENCE AND SPECIAL SUPPORT PROGRAM, BASIC INFRASTRUCTURE PROGRAM (BIP), MULTI-PURPOSE BUILDINGS/FACILITIES TO SUPPORT SOCIAL SERVICES, CONSTRUCTION (COMPLETION) OF MULTI-PURPOSE BUILDING (COVERED COURT) AT BARANGAY CALUMPANG WEST, SAN LUIS, BATANGASCompleted₱14.8M
25DE0095May 20, 2025CONVERGENCE AND SPECIAL SUPPORT PROGRAM, SUSTAINABLE INFRASTRUCTURE PROJECTS ALLEVIATING GAPS (SIPAG), ACCESS ROADS AND/OR BRIDGES FROM THE NATIONAL ROAD/S LEADING TO MAJOR/STRATEGIC PUBLIC BUILDINGS/FACILITIES, IMPROVEMENT OF ROAD, DULANGAN-TALON-ABIACAOCompleted₱144.8M
25DE0096May 20, 2025CONVERGENCE AND SPECIAL SUPPORT PROGRAM, SUSTAINABLE INFRASTRUCTURE PROJECTS ALLEVIATING GAPS (SIPAG), ACCESS ROADS AND/OR BRIDGES FROM THE NATIONAL ROAD/S LEADING TO MAJOR/STRATEGIC PUBLIC BUILDINGS/FACILITIES, IMPROVEMENT OF ROAD, MANGGAHAN-SAN MARTIN-SCompleted₱144.8M
25DE0097May 20, 2025CONVERGENCE AND SPECIAL SUPPORT PROGRAM, SUSTAINABLE INFRASTRUCTURE PROJECTS ALLEVIATING GAPS (SIPAG), ACCESS ROADS AND/OR BRIDGES FROM THE NATIONAL ROAD/S LEADING TO MAJOR/STRATEGIC PUBLIC BUILDINGS/FACILITIES, IMPROVEMENT OF ROAD, BAGONG TUBIG-SAN ISIDRCompleted₱144.8M

Contract amounts as DPWH lists them, not payments. A contract alone does not establish irregularity.