FY2026 GAA: ₱6.79T
PisoScan

Project 19DM0011

DPWH infrastructure contract
Contract ID:
19DM0011
Fingerprint:
7e8ce45528f0b6…fcfdb2c242 Verified
Status:
Completed
Physical progress:
100%
Timeline:
Start Jul 15, 2019 (7 yrs 4 mo ago) · Target/actual end Dec 11, 2019
Description:
ASSET PRESERVATION PROGRAM: PREVENTIVE MAINTENANCE - TERTIARY ROADS - CATANAUAN-BUENAVISTA RD - K0255+335 - K0255+868, K0261+901 - K0262+153, CATANAUAN, QUEZON
Category:
Roads
Implementing office:
DPWH Quezon 3rd DEO · Region IV-A
Contractor:
I.A. BOSQUE CONSTRUCTION CORPORATION · DPWH contractor code 12597
As listed: I.A . BOSQUE CONSTRUCTION CORPORATION
Contract amount:
₱13,007,540.00 (₱13.0M)
Funding source:
Regular Infra - GAA 2019 OO-1
Budget year:
2019

Matching PhilGEPS award entries (same contractor, same contract ID)

RecordDateProcuring entityAmount
686036c1714c…Jun 20, 2019DEPARTMENT OF PUBLIC WORKS AND HIGHWAYS - QUEZON 3RD ED₱12,747,837.19

Other DPWH contracts in the same city / municipality

View all
ContractStartDescriptionStatusAmount
25DM0176Jan 14, 2026CONSTRUCTION OF CLASSROOMS, MABINI ES, UNISAN, QUEZONOn-Going₱9.4M
25DM0182Jan 14, 2026CONSTRUCTION OF CLASSROOMS, UNISAN CENTRAL ELEMENTARY SCHOOL, UNISAN, QUEZONOn-Going₱5.0M
25DM0188Jan 12, 2026CONSTRUCTION OF SHOOL HEALTH FACILITIES, CATANAUAN CS, CATANAUAN, QUEZONCompleted₱4.8M
25DM0151Aug 18, 2025CONSTRUCTION OF MULTI-PURPOSE BUILDING, BONDOC PENINSULA DISTRICT HOSPITAL, CATANAUAN, QUEZONOn-Going₱93.5M
25DM0077Jun 30, 2025CONSTRUCTION OF ROAD, SITIO PIER, BARANGAY SAN ANTONIO PALA, MUNICIPALITY OF CATANAUAN, QUEZONCompleted₱9.6M
25DM0138Jun 30, 2025CONSTRUCTION OF FLOOD MITIGATION, STRUCTURE ALONG BINGABING CREEK, BRGY. MADULAO, CATANAUAN, QUEZONOn-Going₱48.5M
25DM0144Jun 30, 2025CONSTRUCTION OF BRGY BOLO ROAD, CATANAUAN, QUEZONCompleted₱24.2M
25DM0147Jun 30, 2025CONSTRUCTION OF DRAINAGE SYSTEM, BRGY. MADULAO, CATANAUAN, QUEZONOn-Going₱48.5M

Contract amounts as DPWH lists them, not payments. A contract alone does not establish irregularity.