Project 19DN0134

DPWH infrastructure contract
Contract ID:
19DN0134
Fingerprint:
d404fc2324d7c0…54b2daab41 Verified
Status:
Completed
Physical progress:
100%
Timeline:
Start Jul 15, 2019 (7 yrs 4 mo ago) · Target/actual end Nov 11, 2019
Description:
CONCRETING/REHABILITATION OF ROADS SAN LORENZO RUIZ, BRGY. STA. ANA/SAN JUAN, TAYTAY, RIZAL
Category:
Roads
Implementing office:
DPWH Rizal 1st DEO · Region IV-A
Contractor:
QUATRIX CONSTRUCTION AND SUPPLY INC. · DPWH contractor code 44328
Contract amount:
₱7,202,141.89 (₱7.2M)
Funding source:
Regular Infra - GAA 2019 LP
Budget year:
2019

Matching PhilGEPS award entries (same contractor, same contract ID)

RecordDateProcuring entityAmount
8ad5329b3835…Jul 2, 2019DEPARTMENT OF PUBLIC WORKS AND HIGHWAYS - RIZAL 1ST ED₱7,202,141.89

Other DPWH contracts in the same city / municipality

View all
ContractStartDescriptionStatusAmount
25O00107Jun 5, 2025REHABILITATION AND IMPROVEMENT OF RETARDING POND AT TAPAYAN PUMPING STATION AND TRIBUTARIES, PASIG CITYOn-Going₱189.1M
25OB0268May 20, 2025REHABILITATION OF DRAINAGE SYSTEM AT BARANGAY PINAGBUHATAN, PASIG CITY (PHASE 5)On-Going₱14.0M
25OB0269May 20, 2025REHABILITATION OF DRAINAGE SYSTEM AT BARANGAY PINAGBUHATAN, PASIG CITY (PHASE 6)On-Going₱14.0M
25OB0270May 20, 2025REHABILITATION OF DRAINAGE SYSTEM AT BARANGAY PINAGBUHATAN, PASIG CITY (PHASE 7)On-Going₱14.0M
25DN0069Apr 8, 2025CONSTRUCTION OF ROAD AT ROAD 11, 12, 13, 14, 15, 16 AND 17, PUROK 3, LUPANG ARENDA, BARANGAY STA. ANA, TAYTAY, RIZAL (FIRST DISTRICT)On-Going₱19.6M
25DN0063Mar 27, 2025CONSTRUCTION OF MULTI-PURPOSE FACILITY, RIZAL POLICE PROVINCIAL OFFICE, BARANGAY DOLORES, TAYTAY, RIZAL (FIRST DISTRICT)On-Going₱9.7M
25DN0080Mar 27, 2025CONSTRUCTION OF ROAD AT BLK. 16 AND 17, PUROK 2 LUPANG ARENDA, BARANGAY STA. ANA, TAYTAY, RIZAL (FIRST DISTRICT)On-Going₱15.2M
25DN0048Mar 26, 2025CONSTRUCTION OF FLOOD CONTROL STRUCTURE AT TAYTAY RIVER, BARANGAY STA. ANA, TAYTAY, RIZAL (FIRST DISTRICT)On-Going₱49.0M

Contract amounts as DPWH lists them, not payments. A contract alone does not establish irregularity.