PisoScan

Project 19DQ0101

DPWH infrastructure contract
Contract ID:
19DQ0101
Fingerprint:
3f201473e3a9d7…feac3c96b0 Verified
Status:
Completed
Physical progress:
100%
Timeline:
Start Aug 20, 2019 (7 yrs 2 mo ago) · Target/actual end Dec 5, 2019
Description:
LOCAL PROGRAM- LOCAL INFRASTRUCTURE PROGRAM - NATIONAL ROADS AND BRIDGES - NATIONAL ROADS - ASPHALT OVERLAY OF CAVITE-BATANGAS ROAD K0039+000 TO K0040+500 WITH EXCEPTION, SILANG, CAVITE AND ASPHALT OVERLAY OF DASMARIÑAS - CARMONA ROAD K0039+500 - K0041+00
Category:
Roads
Implementing office:
DPWH Region IV-A · Region IV-A
Contractor:
ROBIG BUILDERS AND DEVELOPMENT CORP. · DPWH contractor code 35327
Contract amount:
₱59,399,276.53 (₱59.4M)
Funding source:
Regular Infra - GAA 2019 LP
Budget year:
2019

Other DPWH contracts in the same city / municipality

View all
ContractStartDescriptionStatusAmount
25DQ0114Aug 13, 2025REHABILITATION OF ROAD, BARANGAY KALUBKOB, SILANG, CAVITECompleted₱9.6M
25DQ0109Jul 2, 2025CAPITAL OUTLAY - CONVERGENCE AND SPECIAL SUPPORT PROGRAM - RAINWATER COLLECTOR SYSTEM - VICENTE P. VILLANUEVA MEMORIAL SCHOOL, DASMARIÑAS CITY, CAVITE; MALINTA ELEMENTARY SCHOOL, BRGY. SAMPALOC II, DASMARIÑAS CITY, CAVITE; CAVITE STATE UNIVERSITY, BRGY.On-Going₱2.6M
25DQ0083Jun 26, 2025CONSTRUCTION OF ROAD WITH DRAINAGE, BARANGAY LANGKAAN 2, DASMARINAS CITY, CAVITEOn-Going₱48.0M
25DQ0089Jun 26, 2025CONSTRUCTION OF BANK AND SLOPE STRUCTURES AND OTHER IMPROVEMENTS ALONG CARMONA RIVER, FROM BRGY BULIHAN TO BRGY IPIL, SILANG, CAVITEOn-Going₱97.2M
25DQ0095Jun 26, 2025CONSTRUCTION OF ROAD NETWORK FROM HOSTEL TO ACADEMICS BUILDING, PNPA, CAMP GENERAL MARIANO N. CASTAÑEDA, SILANG, CAVITEOn-Going₱20.8M
25DQ0107Jun 5, 2025OPENING AND CONCRETING OF BRGY. MALABAG FMR, BRGY. MALABAG, SILANG, CAVITECompleted₱5.8M
25DQ0108Jun 5, 2025CONCRETING OF BRGY. IBA FMR, BRGY. IBA, SILANG, CAVITECompleted₱14.5M
25DQ0026Apr 16, 2025REHABILITATION OF MULTI-PURPOSE BUILDING, BARANGAY MAGUYAM, SILANG, CAVITECompleted₱4.9M

Contract amounts as DPWH lists them, not payments. A contract alone does not establish irregularity.