Project 19DQ0119
DPWH infrastructure contract
Contract ID:
19DQ0119
Fingerprint:
e19c3b643611fe…50058aebf0 Verified
Status:
Completed
Physical progress:
100%
Timeline:
Start Sep 9, 2019 (7 yrs 2 mo ago) · Target/actual end Aug 22, 2020
Description:
CONSTRUCTION OF 4STY16CL, BANCAL ES, CARMONA, CAVITE
Category:
Buildings and Facilities
Implementing office:
DPWH Region IV-A · Region IV-A
Contractor:
OMNICON BUILDERS · DPWH contractor code 22816
Contract amount:
₱46,540,639.47 (₱46.5M)
Funding source:
Outside Infra - GAA 2019 DepEd BEFF
Budget year:
2019
Matching PhilGEPS award entries (same contractor, same contract ID)
| Record | Date | Procuring entity | Amount |
|---|---|---|---|
| 71c77be113d0… | Aug 19, 2019 | DEPARTMENT OF PUBLIC WORKS AND HIGHWAYS - CARMONA | ₱45,168,619.79 |
Other DPWH contracts in the same city / municipality
View all| Contract | Start | Description | Status | Amount |
|---|---|---|---|---|
| 26DQ0016 | Jun 16, 2026 | PREVENTIVE MAINTENANCE - PRIMARY ROADS - MANILA-CAVITE (NCR BDRY-JCT CAVITE CITY SECT) - K0017 + 027 - K0017 + 479 | On-Going | ₱21.0M |
| 25DQ0004 | Apr 16, 2025 | CONSTRUCTION/ MAINTENANCE OF FLOOD MITIGATION STRUCTURES AND DRAINAGE SYSTEMS - CONSTRUCTION OF REVETMENT ALONG CARMONA-BIÑAN RIVER, PHASE 1, BARANGAY LANTIC, CARMONA CITY, CAVITE | On-Going | ₱81.7M |
| 25DQ0011 | Apr 16, 2025 | CONSTRUCTION/ MAINTENANCE OF FLOOD MITIGATION STRUCTURES AND DRAINAGE SYSTEMS - CONSTRUCTION OF REVETMENT ALONG CARMONA-BIÑAN RIVER, PHASE 2, BARANGAY LANTIC, CARMONA CITY, CAVITE | On-Going | ₱81.4M |
| 25DQ0015 | Apr 16, 2025 | CONSTRUCTION OF REVETMENT ALONG CARMONA RIVER, PHASE 2, BARANGAY CABILANG BAYBAY, CARMONA CITY, CAVITE | Completed | ₱83.0M |
| 25DQ0072 | Apr 16, 2025 | CONSTRUCTION OF MULTI-PURPOSE BUILDING, BARANGAY POB 3, GENERAL MARIANO ALVAREZ, CAVITE | Completed | ₱4.9M |
| 25DQ0081 | Apr 16, 2025 | CONSTRUCTION OF REVETMENT ALONG CARMONA RIVER, BARANGAY MABUHAY TO BARANGAY LANTIC, PHASE 1, CARMONA CITY, CAVITE | On-Going | ₱93.7M |
| 25DQ0088 | Apr 16, 2025 | CONSTRUCTION OF SLOPE PROTECTION WORKS ALONG CARMONA RIVER, PHASE 1, GEN. MARIANO ALVAREZ, CAVITE | On-Going | ₱94.8M |
| 25DQ0103 | Apr 16, 2025 | CONSTRUCTION OF DPWH QUALITY ASSURANCE LABORATORY BUILDING, DPWH CAVITE 3RD DISTRICT ENGINEERING OFFICE, CARMONA CITY, CAVITE | On-Going | ₱19.4M |
Contract amounts as DPWH lists them, not payments. A contract alone does not establish irregularity.