Project 19ED0003
DPWH infrastructure contract
Contract ID:
19ED0003
Fingerprint:
9c5f7042a3f004…f18900fd4c Verified
Status:
Completed
Physical progress:
100%
Timeline:
Start Jul 25, 2019 (7 yrs 3 mo ago) · Target/actual end Dec 18, 2019
Description:
OFF - CARRIAGEWAY IMPROVEMENT ALONG CALAPAN SOUTH ROAD JCT. POLA RD. K0063+550 - K0064+186, K0064+615 - K0064+993, K0066+220 - K0066+490, K0067+470 - K0067+868.50, POLA, ORIENTAL MINDORO
Category:
GAA 2019 OO-1
Implementing office:
DPWH Mindoro Oriental DEO · MIMAROPA Region
Contractor:
L.N. SALVADOR CONSTRUCTION CORP. (FOR: L.N. SALVADOR CONSTRUCTION) · DPWH contractor code 16661
Contract amount:
₱51,474,196.97 (₱51.5M)
Funding source:
Regular Infra - GAA 2019 OO-1
Budget year:
2019
Matching PhilGEPS award entries (same contractor, same contract ID)
| Record | Date | Procuring entity | Amount |
|---|---|---|---|
| 826a7e37376a… | Jul 9, 2019 | DEPARTMENT OF PUBLIC WORKS AND HIGHWAYS - MINDORO ORIENTAL D | ₱46,794,901.43 |
Other DPWH contracts in the same city / municipality
View all| Contract | Start | Description | Status | Amount |
|---|---|---|---|---|
| 25ED0135 | May 26, 2025 | REHABILITATION OF BRGY. MALUANLUAN - BRGY. MALIBAGO ROAD, POLA, ORIENTAL MINDORO | Completed | ₱144.1M |
| 25ED0112 | May 21, 2025 | CONSTRUCTION OF KABILANG IBAYO BRIDGE, BRGY. BATUHAN, POLA, ORIENTAL MINDORO | On-Going | ₱34.6M |
| 25ED0162 | May 21, 2025 | REHABILITATION OF MULTI - PURPOSE BUILDING (MUNICIPAL GYMNASIUM) IN POLA, ORIENTAL MINDORO | Completed | ₱14.4M |
| 25ED0178 | May 21, 2025 | REHABILITATION OF DRAINAGE CANAL AT SITIO SAMPALOCAN CAMPAMENTO, POLA, ORIENTAL MINDORO | Completed | ₱4.9M |
| 25E00224 | Apr 6, 2025 | BRIDGE PROGRAM- CASILIGAN BRIDGE (B00028MR) ALONG CSR JCT. - POLA ROAD, POL;A, OR. MINDORO | On-Going | ₱24.6M |
| 25EI0105 | Mar 25, 2025 | CONSTRUCTION OF MULTI-PURPOSE BUILDING (EVACUATION CENTER) AT BARANGAY PILI, PINAMALAYAN, ORIENTAL MINDORO | Completed | ₱4.9M |
| 25ED0099 | Mar 18, 2025 | REHABILITATION OF BRIDGE, KABILANG IBAYO, BARANGAY BATUHAN, POLA, ORIENTAL MINDORO | On-Going | ₱14.7M |
| 25ED0054 | Feb 28, 2025 | CONSTRUCTION OF MULTI - PURPOSE BUILDING, BARANGAY BACAWAN, POLA, ORIENTAL MINDORO | Completed | ₱4.9M |
Contract amounts as DPWH lists them, not payments. A contract alone does not establish irregularity.