Project 19EH0031
DPWH infrastructure contract
Contract ID:
19EH0031
Fingerprint:
603723291c753b…1bcb1b910b Verified
Status:
Terminated
Physical progress:
69.6%
Timeline:
Start Aug 6, 2019 (7 yrs 3 mo ago) · Target/actual end Dec 14, 2020
Description:
REHABILITATION/RECONSTRUCTION OF ROADS WITH SLIPS, SLOPE COLLAPSE AND LANDSLIDE ALONG PARPAGOHA (MARIGONDON) - BINOOG ROAD, K0020 + 900 - K0020 + 958.50 (AS PER SURVEY), TABLAS ISLAND, ROMBLON
Category:
GAA 2019 OO-1
Implementing office:
DPWH Romblon DEO · MIMAROPA Region
Contractor:
LEGACY CONSTRUCTION CORPORATION (FORMERLY: LEGACY CONSTRUCTION) · DPWH contractor code 22465
Contract amount:
₱48,198,758.56 (₱48.2M)
Funding source:
Regular Infra - GAA 2019 OO-1
Budget year:
2019
Matching PhilGEPS award entries (same contractor, same contract ID)
| Record | Date | Procuring entity | Amount |
|---|---|---|---|
| 93404a265d6c… | Jul 31, 2019 | DEPARTMENT OF PUBLIC WORKS AND HIGHWAYS - ROMBLON DEO | ₱48,220,584.24 |
Other DPWH contracts in the same city / municipality
View all| Contract | Start | Description | Status | Amount |
|---|---|---|---|---|
| 25EH0167 | Jul 29, 2025 | CONSTRUCTION OF 7 RAINWATER COLLECTION SYSTEM (RWCS), TABLAS ISLAND, ROMBLON | Completed | ₱2.6M |
| 25EH0151 | May 27, 2025 | CONSTRUCTION OF ROAD, AGPUDLOS LEADING TO RSU ROAD (PHASE 3), SAN ANDRES, ROMBLON | On-Going | ₱46.7M |
| 25EH0121 | May 21, 2025 | CONSTRUCTION OF VICTORIA RIVER FLOOD CONTROL STRUCTURE, SAN ANDRES, ROMBLON | On-Going | ₱119.4M |
| 25EH0030 | Apr 11, 2025 | CONSTRUCTION OF MABINI FLOOD CONTROL STRUCTURE, BARANGAY MABINI, SAN ANDRES, ROMBLON | On-Going | ₱48.3M |
| 25EH0090 | Apr 10, 2025 | CONSTRUCTION OF MARI-SUR FLOOD CONTROL STRUCTURE (RIGHT SIDE), SAN ANDRES, ROMBLON | On-Going | ₱48.3M |
| 25EH0012 | Mar 24, 2025 | CONSTRUCTION (COMPLETION) OF MULTI-PURPOSE BUILDING (BARANGAY HALL), BARANGAY VICTORIA, SAN ANDRES, ROMBLON | Completed | ₱4.9M |
| 25EH0062 | Mar 3, 2025 | CONSTRUCTION (COMPLETION) OF MULTI-PURPOSE BUILDING (COVERED COURT), BARANGAY MABINI, SAN ANDRES, ROMBLON | Completed | ₱2.9M |
| 24EH0131 | Jun 19, 2024 | REHABILITATION/RECONSTRUCTION OF ROADS WITH SLIPS, SLOPE COLLAPSE, AND LANDSLIDE ALONG PARPAGOHA (MARIGONDON)-BINOOG RD, K0020+900.00 - K0020+985.60, TABLAS ISLAND, ROMBLON | On-Going | ₱82.0M |
Contract amounts as DPWH lists them, not payments. A contract alone does not establish irregularity.