Project 19FA0080
DPWH infrastructure contract
Contract ID:
19FA0080
Fingerprint:
02eca798275290…96d63ec403 Verified
Status:
Completed
Physical progress:
100%
Timeline:
Start Oct 16, 2019 (7 yrs 1 mo ago) · Target/actual end Sep 10, 2020
Description:
CLUSTER 44-REHAB/RESTORATION/RECONSTRUCTION OF COMUN FC DOWNSTREAM, MALINAO,ALBAY; TAYHI RC,TABACO CITY AND BAGONG SAN ROQUE SITE 1 RC, STO. DOMINGO, ALBAY
Category:
Flood Control and Drainage
Implementing office:
DPWH Albay 1st DEO · Region V
Contractor:
PRECIOUS CONSTRUCTION · DPWH contractor code 32995
Contract amount:
₱84,748,616.00 (₱84.7M)
Funding source:
Outside Infra - GAA 2019 NDRRMF
Budget year:
2019
Matching PhilGEPS award entries (same contractor, same contract ID)
| Record | Date | Procuring entity | Amount |
|---|---|---|---|
| d5dc4c08f9de… | Sep 30, 2019 | DEPARTMENT OF PUBLIC WORKS AND HIGHWAYS - ALBAY 1ST DEO | ₱80,916,506.90 |
Other DPWH contracts in the same city / municipality
View all| Contract | Start | Description | Status | Amount |
|---|---|---|---|---|
| 25FA0026 | Jun 25, 2025 | PREVENTIVE MAINTENANCE-SECONDARY ROADS:DAANG MAHARLIKA JCT-LEGAZPI-STO. DOMINGO-TABACO-CAM. SUR BDRY. ROAD K0561+022-K0561+552 | On-Going | ₱42.6M |
| 25FA0017 | Mar 7, 2025 | CONSTRUCTION OF RIVER CONTROL, MALOLOS, MALINAO, ALBAY | Completed | ₱38.6M |
| 25FA0007 | Feb 21, 2025 | CONSTRUCTION OF SLOPE PROTECTION WORKS AT SAGPAN KAN BANWA CIS, MALINAO, ALBAY | Completed | ₱13.9M |
| 24FA0063 | Oct 7, 2024 | CONSTRUCTION OF 2STY6CL, OGOB ELEMENTARY SCHOOL, MALINAO, ALBAY | On-Going | ₱35.7M |
| 24F00425 | Sep 20, 2024 | CAPITAL OUTLAY - DOH HEALTH FACILITIES ENHANCEMENT PROGRAM (HFEP) - CONSTRUCTION OF NEW SUPER HEALTH CENTERS/RHU - MALINAO SUPER HEALTH CENTER, ALBAY, MALINAO, ALBAY (1ST LEGISLATIVE DISTRICT) | On-Going | ₱11.9M |
| 24FA0056 | Aug 16, 2024 | CLUSTER 13- ASPHALT OVERLAY MAHARLIKA JCT LEGAZPI-STO. DOMINGO-TABACO-CAM SUR BDRY ROAD K0560+395-K0561+022, MALINAO, ALBAY AND ASPHALT OVERLAY- LIGAO-TABACO ROAD K0520+379-K0520+723, TABACO CITY, ALBAY | Completed | ₱79.4M |
| 23FA0091 | Jun 26, 2024 | CLUSTER 29- CONST. OF ELEM. SCHOOL BLDGS. (CLASSROOMS) IN THE FIRST DISTRICT OF ALBAY | Completed | ₱41.4M |
| 24FA0038 | Jun 26, 2024 | RAINWATER COLLECTORS IN PUBLIC FACILITIES IN THE FIRST DISTRICT OF ALBAY | On-Going | ₱2.9M |
Contract amounts as DPWH lists them, not payments. A contract alone does not establish irregularity.