Project 19FF0041

DPWH infrastructure contract
Contract ID:
19FF0041
Fingerprint:
f3547928a96673…3df04dc9de Verified
Status:
Completed
Physical progress:
100%
Timeline:
Start Jun 27, 2019 (7 yrs 4 mo ago) · Target/actual end Dec 15, 2020
Description:
CY-2019 NETWORK DEVELOPMENT - CONSTRUCTION OF MISSING LINK/NEW ROAD, MANAGNAG (TIGAON-GOA-SAN JOSE-LAGONOY-GUIJALO VIA SAN VICENTE ROAD) -HIMANAG ROADSTA.0+750.00 - STA.1+300.00LAGONOY, CAMARINES SUR
Category:
Roads
Implementing office:
Contractor:
PRECIOUS CONSTRUCTION · DPWH contractor code 32995
Contract amount:
₱23,149,166.04 (₱23.1M)
Funding source:
Regular Infra - GAA 2019 OO-1
Budget year:
2019

Matching PhilGEPS award entries (same contractor, same contract ID)

RecordDateProcuring entityAmount
41fa1c7e3099…Jun 11, 2019DEPARTMENT OF PUBLIC WORKS AND HIGHWAYS - CAMARINES SUR 3RD₱23,149,166.04

Other DPWH contracts in the same city / municipality

View all
ContractStartDescriptionStatusAmount
25FG0099Jul 8, 2025CONSTRUCTION OF MULTI-PURPOSE BUILDING, LAGONOY, CAMARINES SUROn-Going₱47.5M
25FG0068Jun 26, 2025CONSTRUCTION OF FLOOD MITIGATION STRUCTURE (DRAINAGE SYSTEM) BARANGAY SAN RAFAEL TO SAN ISIDRO SUR HIGHWAY), LAGONOY, CAMARINES SUROn-Going₱4.7M
25FG0051Jun 25, 2025CONSTRUCTION OF ROAD WITH DRAINAGE ALONG TIGAON-GOA-SAN JOSE-LAGONOY-GUIJALO VIA SAN VICENTE ROAD, BARANGAY SAN RAFAEL SECTIONLAGONOY, CAMARINES SUROn-Going₱9.4M
25FG0030Apr 4, 2025CONSTRUCTION OF MISSING LINKS/NEW ROADS, LALUD-GARCHITORENA ROAD (DEL CARMEN SECTION), CAMARINES SUR, LAGONOY, CAMARINES SUROn-Going₱65.4M
25FG0029Mar 31, 2025CONSTRUCTION OF DRAINAGE CANAL AT CRIS, LAGONOY, CAMARINES SUROn-Going₱9.6M
25FG0032Mar 31, 2025CONSTRUCTION OF DRAINAGE CANAL AT CRIS, BARANGAY LOHO, LAGONOY, CAMARINES SUROn-Going₱14.4M
25F00127Mar 12, 2025ORGANIZATIONAL OUTCOME 2: PROTECT LIVES AND PROPERTIES AGAINST MAJOR FLOODS-FLOOD MANAGEMENT PROGRAM-CONSTRUCTION/REHABILITATION OF FLOOD MITIGATION FACILITIES WITHIN MAJOR RIVER BASINS AND PRINCIPAL RIVERS-CONSTRUCTION OF FLOOD MITIGATION STRUCTURE, LAGOOn-Going₱159.0M
25F00128Mar 12, 2025ORGANIZATIONAL OUTCOME 2: PROTECT LIVES AND PROPERTIES AGAINST MAJOR FLOODS-FLOOD MANAGEMENT PROGRAM-CONSTRUCTION/REHABILITATION OF FLOOD MITIGATION FACILITIES WITHIN MAJOR RIVER BASINS AND PRINCIPAL RIVERS-CONSTRUCTION OF FLOOD MITIGATION STRUCTURE, LAGOOn-Going₱154.3M

Contract amounts as DPWH lists them, not payments. A contract alone does not establish irregularity.