Project 19GA0007
DPWH infrastructure contract
Contract ID:
19GA0007
Fingerprint:
c2f15631e933a2…8afe5a288e Verified
Status:
Completed
Physical progress:
100%
Timeline:
Start Jul 12, 2019 (7 yrs 4 mo ago) · Target/actual end Aug 24, 2019
Description:
CONCRETING OF ROAD, BRGY. BANAYBANAY, MALINAO, AKLAN
Category:
Roads
Implementing office:
DPWH Aklan DEO · Region VI
Contractor:
SILVERROCK CONSTRUCTION & SUPPLY · DPWH contractor code 38216
Contract amount:
₱891,718.87 (₱891.7K)
Funding source:
Regular Infra - GAA 2019 LP
Budget year:
2019
Matching PhilGEPS award entries (same contractor, same contract ID)
| Record | Date | Procuring entity | Amount |
|---|---|---|---|
| af2f947499fd… | Jun 27, 2019 | DEPARTMENT OF PUBLIC WORKS AND HIGHWAYS - AKLAN DEO | ₱891,718.87 |
Other DPWH contracts in the same city / municipality
View all| Contract | Start | Description | Status | Amount |
|---|---|---|---|---|
| 25GA0157 | Sep 18, 2025 | CONSTRUCTION OF SCHOOL BUILDING, KALIBO PILOT ELEMENTARY SCHOOL, BARANGAY POBLACION, KALIBO, AKLAN | On-Going | ₱14.9M |
| 24GA0253 | Aug 20, 2025 | REHABILITATION OF CONCRETING OF ALIPUTOS FMR, BRGY. ALIPUTOS, NUMANCIA, AKLAN | On-Going | ₱8.3M |
| 25GA0023 | Jun 4, 2025 | CONSTRUCTION OF REVETMENT WALL ALONG AKLAN RIVER, BRGY. BACHAO SUR, KALIBO, AKLAN | On-Going | ₱60.8M |
| 25GA0122 | May 26, 2025 | CONSTRUCTION OF KALIBO GYMNASIUM, BARANGAY BAKHAW NORTE, KALIBO, AKLAN | On-Going | ₱98.5M |
| 25GA0121 | May 23, 2025 | CONSTRUCTION OF REVETMENT WALL IN BRGY. BAKHAW NORTE, KALIBO, AKLAN | On-Going | ₱9.6M |
| 25GA0040 | Apr 3, 2025 | CONSTRUCTION OF MABULAY ROAD, BARANGAY LINABUAN NORTE, KALIBO, AKLAN | Completed | ₱4.9M |
| 25GA0001 | Mar 21, 2025 | AKLAN EAST RD - K0281+000 - K0283+085 | On-Going | ₱93.6M |
| 24GA0251 | Mar 19, 2025 | CONSTRUCTION OF REVETMENT WALL (FLOOD CONTROL), ALONG AKLAN RIVER, KALIBO, AKLAN | On-Going | ₱24.1M |
Contract amounts as DPWH lists them, not payments. A contract alone does not establish irregularity.