Skip to content
FY2026 GAA: ₱6.79T
PisoScan

Project 19GB0094

DPWH infrastructure contract
Contract ID:
19GB0094
Fingerprint:
8fc1888270b79f…9dab5df9fe Verified
Status:
Completed
Physical progress:
100%
Timeline:
Start Jun 24, 2019 (7 yrs 4 mo ago) · Target/actual end Mar 10, 2020
Description:
CONSTRUCTION OF REVETMENT - CONSTRUCTION OF REVETMENT WALL ALONG CANGARANAN RIVER, BARBAZA, ANTIQUE
Category:
Flood Control and Drainage
Implementing office:
DPWH Antique DEO · Region VI
Contractor:
AUDRIC CONSTRUCTION & SUPPLY · DPWH contractor code 34376
Contract amount:
₱29,299,999.99 (₱29.3M)
Funding source:
Regular Infra - GAA 2019 OO-2
Budget year:
2019

Matching PhilGEPS award entries (same contractor, same contract ID)

RecordDateProcuring entityAmount
1c75c7c55ec3…May 31, 2019DEPARTMENT OF PUBLIC WORKS AND HIGHWAYS - ANTIQUE DEO₱29,299,999.99

Other DPWH contracts in the same city / municipality

View all
ContractStartDescriptionStatusAmount
25G00014Mar 24, 2025SABANG WEST ROAD (TURTLE BEACH NESTING BOULEVARD AND SUNSET VIEWING) BUGASONG, ANTIQUECompleted₱8.1M
25GB0039Mar 4, 2025REHABILITATION/MAJOR REPAIR OF BRIDGE- TUL-ANG BR. (B00329PN) ALONG ILOILO-ANTIQUE RD BUGASONG,ANTIQUECompleted₱14.7M
25GB0009Feb 28, 2025CONSTRUCTION OF FLOOD CONTROL STRUCTURES ALONG PALIWAN RIVER, BUGASONG CIS, BUGASONG, ANTIQUECompleted₱14.7M
25GB0017Feb 28, 2025CONSTRUCTION OF MULTI-PURPOSE BUILDING, BARANGAY SABANG EAST, BUGASONG, ANTIQUECompleted₱4.9M
25G00054Feb 14, 2025CONSTRUCTION OF FLOOD CONTROL STRUCTURE ALONG PALIWAN RIVER, BARANGAY CUBAY NORTH- BARANGAY TICA, BUGASONG, ANTIQUEOn-Going₱128.2M
24GB0134Oct 9, 2024CONCRETING OF SITIO TARUG TO SITIO BULAN BULAN, BRGY. IGBALANGAO, BUGASONG, ANTIQUECompleted₱14.9M
24G00051Apr 19, 2024CONSTRUCTION (COMPLETION) OF PALIWAN BRIDGE INCLUDING RIVER IMPROVEMENT WORKS, BUGASONG, ANTIQUECompleted₱54.5M
24GB0021Apr 8, 2024CONSTRUCTION OF ROAD, BARANGAY TAGUDTOD-BARANGAY MARAY- BARANGAY TONOAN BUGASONG, ANTIQUEOn-Going₱147.4M

Contract amounts as DPWH lists them, not payments. A contract alone does not establish irregularity.