Project 19GD0072
DPWH infrastructure contract
Contract ID:
19GD0072
Fingerprint:
00c952b6e143d0…f56055dc2f Verified
Status:
Completed
Physical progress:
100%
Timeline:
Start Jul 16, 2019 (7 yrs 4 mo ago) · Target/actual end Oct 18, 2019
Description:
CONCRETING OF ROADS, BRGY. CABUG-CABUG, PRES. ROXAS, CAPIZ
Category:
Roads
Implementing office:
DPWH Capiz 1st DEO · Region VI
Contractor:
KIRSKAT VENTURE · DPWH contractor code 32042
Contract amount:
₱3,792,681.28 (₱3.8M)
Funding source:
Regular Infra - GAA 2019 LP
Budget year:
2019
Matching PhilGEPS award entries (same contractor, same contract ID)
| Record | Date | Procuring entity | Amount |
|---|---|---|---|
| 20991db9adb7… | Jun 25, 2019 | DEPARTMENT OF PUBLIC WORKS AND HIGHWAYS - CAPIZ 1ST DEO | ₱3,792,681.28 |
Other DPWH contracts in the same city / municipality
View all| Contract | Start | Description | Status | Amount |
|---|---|---|---|---|
| 25GD0029 | Jun 3, 2025 | CONSTRUCTION OF MULTI-PURPOSE BUILDING, BARANGAY SANTO NINO, PRESIDENT ROXAS, CAPIZ | On-Going | ₱4.9M |
| 25GD0010 | Mar 24, 2025 | CONSTRUCTION OF CONCRETE ROAD - CONSTRUCTION OF ROAD, BARANGAY CULILANG, PRESIDENT ROXAS, CAPIZ | On-Going | ₱4.9M |
| 25GD0013 | Mar 24, 2025 | CONSTRUCTION OF CONCRETE ROAD - CONSTRUCTION OF ROAD, BARANGAY VISCAYA, PRESIDENT ROXAS, CAPIZ | On-Going | ₱7.4M |
| 24GD0024 | Mar 13, 2024 | CONSTRUCTION OF MULTI-PURPOSE BUILDING, BARANGAY HANGLID, PRESIDENT ROXAS, CAPIZ | Completed | ₱4.9M |
| 23GD0076 | Jun 14, 2023 | CONSTRUCTION OF MULTI-PURPOSE BUILDING IN BRGY. PANTALAN, PRES. ROXAS, CAPIZ | Completed | ₱7.6M |
| 23GD0074 | Jun 8, 2023 | CONCRETING OF BRGY.BADIANGON FMR, BRGY. BADIANGON, PRESIDENT ROXAS, CAPIZ | On-Going | ₱8.7M |
| 23GD0064 | Apr 28, 2023 | CONSTRUCTION (COMPLETION) OF MULTI-PURPOSE BUILDING, BARANGAY IBACA, PRESIDENT ROXAS, CAPIZ | Completed | ₱4.1M |
| 23GD0066 | Apr 28, 2023 | CONSTRUCTION (COMPLETION) OF MULTI-PURPOSE BUILDING, BARANGAY BADIANGAN, PRESIDENT ROXAS, CAPIZ | Completed | ₱4.9M |
Contract amounts as DPWH lists them, not payments. A contract alone does not establish irregularity.