Skip to content
FY2026 GAA: ₱6.79T
PisoScan

Project 19GD0073

DPWH infrastructure contract
Contract ID:
19GD0073
Fingerprint:
ab0724596f1f0d…9876779f17 Verified
Status:
Completed
Physical progress:
100%
Timeline:
Start Jul 16, 2019 (7 yrs 4 mo ago) · Target/actual end Aug 14, 2019
Description:
CONCRETING OF ROADS, BRGY. CANAPIAN, MAAYON, CAPIZ
Category:
Roads
Implementing office:
DPWH Capiz 1st DEO · Region VI
Contractor:
MBM CONSTRUCTION · DPWH contractor code 37891
Contract amount:
₱2,844,000.00 (₱2.8M)
Funding source:
Regular Infra - GAA 2019 LP
Budget year:
2019

Matching PhilGEPS award entries (same contractor, same contract ID)

RecordDateProcuring entityAmount
7b02c3bd716a…Jun 25, 2019DEPARTMENT OF PUBLIC WORKS AND HIGHWAYS - CAPIZ 1ST DEO₱2,844,000.00

Other DPWH contracts in the same city / municipality

View all
ContractStartDescriptionStatusAmount
25GD0042Jun 9, 2025CONSTRUCTION OF MULTI-PURPOSE BUILDING, BARANGAY POBLACION, MAAYON, CAPIZOn-Going₱9.9M
25GD0047Jun 9, 2025MAAYON BY-PASS ROAD, CAPIZOn-Going₱4.9M
25G00068Mar 24, 2025CONSTRUCTION OF MULTI- PURPOSE BUILDING (EVACUATION FACILITIES), BARANGAY INDAYAGAN, MAAYON CAPIZOn-Going₱48.2M
25GD0009Mar 24, 2025CONSTRUCTION OF CONCRETE ROAD - CONSTRUCTION OF ROAD, BARANGAY CABANGAHAN, PANITAN, CAPIZCompleted₱4.9M
25GD0015Mar 24, 2025CONSTRUCTION OF MULTI-PURPOSE BUILDING, BARANGAY FERNANDEZ, MAAYON, CAPIZOn-Going₱4.9M
25GH0091Mar 24, 2025CONSTRUCTION (COMPLETION) OF MULTI-PURPOSE BUILDING, BARANGAY LAYOGBATO, LEMERY, ILOILOCompleted₱2.9M
25GD0018Mar 17, 2025CONSTRUCTION OF CONCRETE ROAD - CONSTRUCTION OF ROAD, BARANGAY JEBACA, MAAYON, CAPIZOn-Going₱4.9M
25G00053Mar 6, 2025MAAYON- SARA BYPASS ROAD, CAPIZOn-Going₱36.5M

Contract amounts as DPWH lists them, not payments. A contract alone does not establish irregularity.