Skip to content
FY2026 GAA: ₱6.79T
PisoScan

Project 19GG0127

DPWH infrastructure contract
Contract ID:
19GG0127
Fingerprint:
7cd2a946549e1e…e4919b1ad8 Verified
Status:
Completed
Physical progress:
100%
Timeline:
Start Dec 22, 2019 (6 yrs 10 mo ago) · Target/actual end Feb 24, 2020
Description:
CONCRETING OF BRGY. POLT-AN FMR, BRGY. POLOT-AN, POTOTAN, ILOILO
Category:
Roads
Implementing office:
DPWH Iloilo 2nd DEO · Region VI
Contractor:
SPS BUILDERS · DPWH contractor code 38002
Contract amount:
₱9,451,582.38 (₱9.5M)
Funding source:
Outside Infra - GAA 2019 DA FMR
Budget year:
2019

Matching PhilGEPS award entries (same contractor, same contract ID)

RecordDateProcuring entityAmount
79e5ca69d207…Nov 29, 2019DEPARTMENT OF PUBLIC WORKS AND HIGHWAYS - ILOILO 2ND DISTRIC₱9,451,582.38

Other DPWH contracts in the same city / municipality

View all
ContractStartDescriptionStatusAmount
25GR0058Feb 26, 2026REPAIR/REHABILITATION OF CLASSROOMS, BACAN ES, CABATUAN, ILOILOOn-Going₱4.7M
25GR0059Feb 26, 2026REPAIR/REHABILITATION OF CLASSROOMS, IGANG ES, POTOTAN, ILOILOCompleted₱6.5M
25GR0054Sep 15, 2025IMPROVEMENT OF INTERSECTION AT ILOILO-CAPIZ (NEW ROUTE) - K0029 + 260On-Going₱14.7M
25GR0050Aug 1, 2025CONSTRUCTION (COMPLETION) OF MULTI-PURPOSE BUILDING, POTOTAN, ILOILOOn-Going₱3.7M
25GG0179Jul 7, 2025CONSTRUCTION OF BRIDGE, BARANGAY CATO-OGAN TO BARANGAY CAU-AYAN, POTOTAN, ILOILOOn-Going₱48.9M
25GR0016Jul 7, 2025CONSTRUCTION OF FLOOD CONTROL STRUCTURE ALONG JALAUR RIVER, BARANGAY BONGCO, POTOTAN, ILOILOCompleted₱38.8M
25GR0017Jul 7, 2025CONSTRUCTION OF FLOOD CONTROL STRUCTURE ALONG JALAUR RIVER, BARANGAY CANSILAYAN, POTOTAN, ILOILOOn-Going₱21.5M
25GR0018Jul 7, 2025CONSTRUCTION OF FLOOD CONTROL/SLOPE PROTECTION ALONG SUAGE RIVER, GUIBUANGAN, POTOTAN, ILOILOOn-Going₱19.5M

Contract amounts as DPWH lists them, not payments. A contract alone does not establish irregularity.