Project 19GI0042

DPWH infrastructure contract
Contract ID:
19GI0042
Fingerprint:
f7d771df5f84c5…658b21ff50 Verified
Status:
Completed
Physical progress:
100%
Timeline:
Start Jul 11, 2019 (7 yrs 4 mo ago) · Target/actual end Sep 25, 2019
Description:
COMPLETION OF MULTI-PURPOSE BUILDING ( ILOILO SCIENCE AND TECHNOLOGY UNIVERSITY LEON CAMPUS), BRGY. POBLACION, LEON, ILOILO
Category:
Buildings and Facilities
Implementing office:
DPWH Iloilo 4th DEO · Region VI
Contractor:
MAKANA BUILDERS & SUPPLY · DPWH contractor code 39826
Contract amount:
₱716,958.98 (₱717.0K)
Funding source:
Regular Infra - GAA 2019 LP
Budget year:
2019

Matching PhilGEPS award entries (same contractor, same contract ID)

RecordDateProcuring entityAmount
1adcf6b9ebbc…Jun 24, 2019DEPARTMENT OF PUBLIC WORKS AND HIGHWAYS - ILOILO 4TH DEO₱704,916.06

Other DPWH contracts in the same city / municipality

View all
ContractStartDescriptionStatusAmount
25GI0068Sep 9, 2025CONSTRUCTION OF MULTI-PURPOSE BUILDING, BARANGAY POBLACION, LEON, ILOILOOn-Going₱9.8M
25GI0081Jul 11, 2025CONSTRUCTION OF RAINWATER COLLECTOR SYSTEMCompleted₱2.6M
25GI0059Jun 4, 2025CONSTRUCTION OF MULTI-PURPOSE BUILDING, BARANGAY BINOLBOG, LEON, ILOILOCompleted₱4.9M
25GI0056May 20, 2025CONSTRUCTION OF MULTI-PURPOSE BUILDING, BARANGAY TUOG, LEON, ILOILOCompleted₱4.9M
25GI0057May 20, 2025CONSTRUCTION OF MULTI-PURPOSE BUILDING, BARANGAY IGCADIOS, LEON, ILOILOOn-Going₱4.9M
25GI0058May 20, 2025CONSTRUCTION OF MULTI-PURPOSE BUILDING, BARANGAY TACUYONG SUR, LEON, ILOILOCompleted₱4.9M
25GI0036Mar 25, 2025CONSTRUCTION OF SIBALOM FLOOD CONTROL STRUCTURE, SIBALOM RIVER, BARANGAY NAGBANGI, LEON, ILOILOCompleted₱29.1M
25GI0039Mar 25, 2025CONSTRUCTION OF ROAD SLOPE PROTECTION STRUCTURE - JCT BANCAL-LEON-ANTIQUE BDRY RD - K0042 + 435 - K0042 + 480Completed₱22.3M

Contract amounts as DPWH lists them, not payments. A contract alone does not establish irregularity.