FY2026 GAA: ₱6.79T
PisoScan

Project 19GI0100

DPWH infrastructure contract
Contract ID:
19GI0100
Fingerprint:
f14a3364e96772…16eead5451 Verified
Status:
Completed
Physical progress:
100%
Timeline:
Start Aug 27, 2019 (7 yrs 2 mo ago) · Target/actual end Nov 4, 2019
Description:
CONCRETING OF BRGY. POBLACION FMR, BRGY. POBLACION, NEW LUCENA, ILOILO
Category:
Roads
Implementing office:
DPWH Iloilo 4th DEO · Region VI
Contractor:
PATRILA BUILDERS, INC. · DPWH contractor code 26628
Contract amount:
₱4,974,997.87 (₱5.0M)
Funding source:
Outside Infra - GAA 2019 DA FMR
Budget year:
2019

Matching PhilGEPS award entries (same contractor, same contract ID)

RecordDateProcuring entityAmount
c3188e1df293…Aug 13, 2019DEPARTMENT OF PUBLIC WORKS AND HIGHWAYS - ILOILO 4TH DEO₱4,836,064.10

Other DPWH contracts in the same city / municipality

View all
ContractStartDescriptionStatusAmount
26GI0031Jun 5, 2026PREVENTIVE MAINTENANCE OF ROAD: CONCRETE REBLOCKING - CABATUAN-NEW LUCENA-BANGA-BANTE RD - K0034 + (-766) - K0034 + (-514.25)Completed₱5.3M
25GI0017Feb 18, 2025CONSTRUCTION OF MULTI-PURPOSE BUILDING, NEW LUCENA, ILOILOCompleted₱9.8M
25GI0019Feb 18, 2025CONSTRUCTION OF MULTI-PURPOSE BUILDING, BARANGAY WARI-WARI, NEW LUCENA, ILOILOCompleted₱4.9M
24GI0011May 31, 2024OFF-CARRIAGEWAY IMPROVEMENT: PAVING OF SHOULDERS - CABATUAN-NEW LUCENA-BANGA-BANTE RD - K0037 + 624 - K0038 + 000Completed₱14.7M
24GI0063Mar 12, 2024CONSTRUCTION (COMPLETION) OF MULTI-PURPOSE BUILDING, BARANGAY BALABAG, NEW LUCENA, ILOILOCompleted₱3.0M
24GI0004Feb 14, 2024CONSTRUCTION OF ROAD, SITIO CABUNGA, BARANGAY POBLACION, NEW LUCENA, ILOILOCompleted₱5.9M
24GI0023Feb 14, 2024CONSTRUCTION OF MULTI-PURPOSE BUILDING, BARANGAY BILIDAN, NEW LUCENA, ILOILOCompleted₱4.9M
23GI0118Sep 19, 2023CONSTRUCTION OF MULTI-PURPOSE BUILDING, MUNICIPALITY OF NEW LUCENA, ILOILOCompleted₱5.2M

Contract amounts as DPWH lists them, not payments. A contract alone does not establish irregularity.