Project 19GK0212
DPWH infrastructure contract
Contract ID:
19GK0212
Fingerprint:
5f3132bdf787fe…1f2eaf013b Verified
Status:
Completed
Physical progress:
100%
Timeline:
Start Aug 28, 2019 (7 yrs 2 mo ago) · Target/actual end Jan 27, 2020
Description:
CONSTRUCTION OF FLOOD CONTROL STRUCTURE - CONSTRUCTION OF SEAWALL/FLOOD CONTROL STRUCTURES, BARANGAY ZONE 3, TALISAY CITY, NEGROS OCCIDENTAL
Category:
Flood Control and Drainage
Implementing office:
DPWH Negros Occidental 1st DEO · Negros Island Region
Contractor:
KENBE CONSTRUCTION & SUPPLY · DPWH contractor code 34290
Contract amount:
₱7,447,780.00 (₱7.4M)
Funding source:
Regular Infra - GAA 2019 LP
Budget year:
2019
Matching PhilGEPS award entries (same contractor, same contract ID)
| Record | Date | Procuring entity | Amount |
|---|---|---|---|
| 83bf9f2a1ce3… | Aug 9, 2019 | DEPARTMENT OF PUBLIC WORKS AND HIGHWAYS - NEG. OCC. 1ST DEO | ₱7,447,780.00 |
Other DPWH contracts in the same city / municipality
View all| Contract | Start | Description | Status | Amount |
|---|---|---|---|---|
| 26RA0125 | Jun 23, 2026 | PREVENTIVE MAINTENANCE OF ROAD: ASPHALT OVERLAY - BACOLOD NORTH RD - K0009 + 100 - K0009 + 520 | On-Going | ₱15.4M |
| 25RA0029 | Apr 8, 2026 | CONSTRUCTION OF FARM-TO-MILL ROAD, BARANGAY BAGTIC, SILAY CITY, NEGROS OCCIDENTAL | On-Going | ₱22.2M |
| 25RA0028 | Mar 25, 2026 | CONSTRUCTION OF FARM-TO-MILL ROAD, BARANGAY XVIII-A ROAD SECTION, VICTORIAS CITY, NEGROS OCCIDENTAL | On-Going | ₱24.8M |
| 25GK0097 | Jun 17, 2025 | CONSTRUCTION OF DRAINAGE STRUCTURE ALONG ROAD -BACOLOD NORTH RD - K0009 + (-273) -K0010+704 | On-Going | ₱24.2M |
| 25GK0021 | Jun 3, 2025 | INSTALLATION/APPLICATION OF ROAD SAFETY FACILITIES (ROADWAY LIGHTING) ALONG SILAY-LANTAWAN RD - K0039 + 200 - K0040 + 366 | On-Going | ₱13.6M |
| 25GK0125 | May 28, 2025 | REHABILITATION OF MULTI-PURPOSE BUILDING, BRGY. CONCEPCION, TALISAY CITY, NEGROS OCCIDENTAL | Completed | ₱6.8M |
| 25GK0127 | May 28, 2025 | REHABILITATION OF MULTI-PURPOSE BUILDING, BRGY. MATAB-ANG, TALISAY CITY, NEGROS OCCIDENTAL | Completed | ₱6.2M |
| 25GK0139 | May 28, 2025 | CONSTRUCTION OF ROAD AT SITIO BALOGO, BRGY. CONCEPCION, TALISAY CITY, NEGROS OCCIDENTAL | On-Going | ₱19.8M |
Contract amounts as DPWH lists them, not payments. A contract alone does not establish irregularity.