Project 19HG0213

DPWH infrastructure contract
Contract ID:
19HG0213
Fingerprint:
fca1e514b56db9…a05391821f Verified
Status:
Completed
Physical progress:
100%
Timeline:
Start Aug 21, 2019 (7 yrs 2 mo ago) · Target/actual end Nov 12, 2019
Description:
CONCRETING OF BRGY. POBLACION - BRGY. MANGACO FMR, BRGY. POBLACION AND BRGY. MANGACO, GINATILAN, CEBU
Category:
Roads
Implementing office:
DPWH Cebu 2nd DEO · Region VII
Contractor:
WORLDWIDE BUILDERS · DPWH contractor code 31408
Contract amount:
₱4,721,512.82 (₱4.7M)
Funding source:
Outside Infra - GAA 2019 DA FMR
Budget year:
2019

Matching PhilGEPS award entries (same contractor, same contract ID)

RecordDateProcuring entityAmount
4a982137ac6f…Aug 5, 2019DEPARTMENT OF PUBLIC WORKS AND HIGHWAYS - CEBU 4TH DEO₱4,721,048.67

Other DPWH contracts in the same city / municipality

View all
ContractStartDescriptionStatusAmount
25HO0151Apr 10, 2025CONVERGENCE AND SPECIAL SUPPORT PROGRAM, BASIC INFRASTRUCTURE PROGRAM (BIP), FLOOD MITIGATION STRUCTURES PROTECTING MAJOR/ STRATEGIC PUBLIC BUILDINGS/ FACILITIES, CONSTRUCTION OF SEAWALL PROTECTION STRUCTURE ALONG SANTANDER-BARILI-TOLEDO ROAD AT SITIO LUTOn-Going₱145.5M
25HO0165Apr 10, 2025CONVERGENCE AND SPECIAL SUPPORT PROGRAM, BASIC INFRASTRUCTURE PROGRAM (BIP), FLOOD MITIGATION PROGRAM STRUCTURES PROTECTING MAJOR/STRATEGIC PUBLIC BUILDINGS/FACILITIES, CONSTRUCTION OF FLOOD CONTROL WALL AT GINATILAN RICER (UPSTREAM), BARANGAY POBLACION -On-Going₱141.9M
25HO0080Mar 17, 2025CONVERGENCE AND SPECIAL SUPPORT PROGRAM, BASIC INFRASTRUCTURE PROGRAM (BIP), ACCESS ROADS AND/OR BRIDGES FROM THE NATIONAL ROAD/S LEADING TO MAJOR/ STRATEGIC PUBLIC BUILDINGS/ FACILITIES, CONSTRUCTION OF SAN ANTONIO BRIDGE, BARANGAY POBLACION, GINATILAN,On-Going₱19.5M
25HO0054Feb 28, 2025ORGANIZATIONAL OUTCOME 2: PROTECT LIVES AND PROPERTIES AGAINST MAJOR FLOODS, FLOOD MANAGEMENT PROGRAM, CONSTRUCTION/ MAINTENANCE OF FLOOD MITIGATION STRUCTURES AND DRAINAGE SYSTEMS, CONSTRUCTION OF SEAWALL, KALUBIHAN, BARANGAY GUIWANON, GINATILAN, CEBUOn-Going₱95.1M
25HO0020Feb 19, 2025CONVERGENCE AND SPECIAL SUPPORT PROGRAM, BASIC INFRASTRUCTURE PROGRAM (BIP ), ACCESS ROADS AND/OR BRIDGES FROM THE NATIONAL ROAD/S LEADING TO MAJOR/ STRATEGIC PUBLIC BUILDINGS/ FACILITIES, CONSTRUCTION OF PALANAS-ADING ROAD, BARANGAY PALANAS, GINATILAN, COn-Going₱9.7M
25HO0021Feb 19, 2025CONVERGENCE AND SPECIAL SUPPORT PROGRAM, BASIC INFRASTRUCTURE PROGRAM (BIP ), ACCESS ROADS AND/OR BRIDGES FROM THE NATIONAL ROAD/S LEADING TO MAJOR/ STRATEGIC PUBLIC BUILDINGS/ FACILITIES, CONSTRUCTION OF ROAD, BARANGAY PALANAS, GINATILAN, CEBUOn-Going₱5.8M
25HO0029Feb 19, 2025CONVERGENCE AND SPECIAL SUPPORT PROGRAM, BASIC INFRASTRUCTURE PROGRAM (BIP), ACCESS ROADS AND/OR BRIDGES FROM THE NATIONAL ROAD/S LEADING TO MAJOR/ STRATEGIC PUBLIC BUILDINGS/ FACILITIES, CONSTRUCTION OF ANAO-CAMBAGTE-MANGACO ROAD, BARANGAY ANAO, CAMBAGTEOn-Going₱9.8M
23HO0303Jan 13, 2025CONVERGENCE AND SPECIAL SUPPORT PROGRAM, SUSTAINABLE INFRASTRUCTURE PROJECTS ALLEVIATING GAPS (SIPAG), ACCESS ROADS AND/OR BRIDGES FROM THE NATIONAL ROAD/S LEADING TO MAJOR/ STRATEGIC PUBLIC BUILDINGS/ FACILITIES, IMPROVEMENT OF MANLUM - SALAMANCA ROAD (POn-Going₱7.1M

Contract amounts as DPWH lists them, not payments. A contract alone does not establish irregularity.