Project 19IA0017
DPWH infrastructure contract
Contract ID:
19IA0017
Fingerprint:
0faacb32cd0a06…e95b5d1065 Verified
Status:
Completed
Physical progress:
100%
Timeline:
Start Jul 2, 2019 (7 yrs 4 mo ago) · Target/actual end Aug 30, 2019
Description:
BRGY. ROAD IMPROVEMENT/CONSTRUCTION, BRGY. BATO, BILIRAN, BILIRAN (11.503966°, 124.434824° TO 11.503591°, 124.434525°) SECTION 1; (11.504184°, 124.435027° TO 11.50463°, 124.435438°) SECTION 2; (11.50857°, 124.44158° TO 11.50821°, 124.44114° ) SECTION 3
Category:
Roads
Implementing office:
DPWH Biliran DEO · Region VIII
Contractor:
W.B. ALAGAO CONSTRUCTION · DPWH contractor code 15622
Contract amount:
₱1,950,000.00 (₱1.9M)
Funding source:
Regular Infra - GAA 2019 LP
Budget year:
2019
Matching PhilGEPS award entries (same contractor, same contract ID)
| Record | Date | Procuring entity | Amount |
|---|---|---|---|
| 2286c72c5565… | Jun 11, 2019 | DEPARTMENT OF PUBLIC WORKS AND HIGHWAYS - BILIRAN ED | ₱1,950,000.00 |
Other DPWH contracts in the same city / municipality
View all| Contract | Start | Description | Status | Amount |
|---|---|---|---|---|
| 26IA0002 | Jun 23, 2026 | REHABILITATION/RECONSTRUCTION OF ROADS WITH SLIPS, SLOPE COLLAPS AND LANDSLIDE - SECONDARY ROADS - BILIRAN CIRCUMFERENTIAL RD - K1012+852 - K1013+083, K1013+839-K1014+009, K1014+603 - K1014+683, K1014+869 - K1014+991 | On-Going | ₱37.9M |
| 25IA0171 | Jan 28, 2026 | REPAIR/REHABILITATION OF CLASSROOMS, BUSALI ES, BILIRAN, BILIRAN | On-Going | ₱3.2M |
| 25IA0161 | Jul 15, 2025 | REHABILITATION OF ROAD, BARANGAY BUSALI, BILIRAN, BILIRAN | On-Going | ₱9.8M |
| 24IA0151 | Apr 10, 2025 | CONCRETING OF FMR- BRGY. PINANGUMHAN, BILIRAN TO BRGY. HAGUIKHIKAN, NAVAL, BILIRAN | On-Going | ₱29.8M |
| 25IA0097 | Mar 25, 2025 | INSTALLATION/APPLICATION OF ROAD SAFETY FACILITIES - BILIRAN CIRCUMFERENTIAL RD. - K1012+150 - K1016+650 | Completed | ₱29.4M |
| 25IA0029 | Feb 28, 2025 | NETWORK DEVELOPMENT - ROAD WIDENING - SECONDARY ROADS - BILIRAN CIRCUMFERENTIAL RD, K1109+364-K1110+542 | On-Going | ₱48.9M |
| 25IA0006 | Feb 26, 2025 | CONSTRUCTION OF SANTOL FLOOD CONTROL STRUCTURE ALONG BILIRAN CIRCUMFERENTIAL ROAD, BILIRAN, BILIRAN | On-Going | ₱48.9M |
| 25IA0018 | Feb 26, 2025 | CONSTRUCTION OF ROAD, BARANGAY BUSALI, BILIRAN, BILIRAN | Completed | ₱14.6M |
Contract amounts as DPWH lists them, not payments. A contract alone does not establish irregularity.