Project 19IG0080
DPWH infrastructure contract
Contract ID:
19IG0080
Fingerprint:
e07bede4966841…d880c742c8 Verified
Status:
Completed
Physical progress:
100%
Timeline:
Start Sep 11, 2019 (7 yrs 2 mo ago) · Target/actual end Nov 24, 2019
Description:
CONSTRUCTION (CONCRETING) OF LOCAL ROADS, HINDANG, LEYTE
Category:
Roads
Implementing office:
DPWH Leyte 5th DEO · Region VIII
Contractor:
C N E CONSTRUCTION · DPWH contractor code 22148
Contract amount:
₱2,910,600.00 (₱2.9M)
Funding source:
Regular Infra - GAA 2019 LP
Budget year:
2019
Other DPWH contracts in the same city / municipality
View all| Contract | Start | Description | Status | Amount |
|---|---|---|---|---|
| 25IG0085 | Sep 18, 2025 | RAINWATER COLLECTOR SYSTEM | Completed | ₱2.6M |
| 25IG0005 | May 20, 2025 | CONSTRUCTION OF ROAD, BARANGAY MABAGON TO BARANGAY MA-ASIN, HINDANG, LEYTE | Completed | ₱4.9M |
| 25IG0041 | May 20, 2025 | CONSTRUCTION OF MULTI-PURPOSE BUILDING, BARANGAY BALDOZA, HINDANG, LEYTE | Completed | ₱4.9M |
| 25IG0045 | May 20, 2025 | CONSTRUCTION (COMPLETION) OF MULTI-PURPOSE BUILDING, BARANGAY CANHA-AYON, HINDANG, LEYTE | Completed | ₱2.0M |
| 25IG0046 | Mar 27, 2025 | NETWORK DEVELOPMENT - CONSTRUCTION OF BY-PASS AND DIVERSION ROADS - HINDANG BY-PASS ROAD, LEYTE | On-Going | ₱19.6M |
| 25IG0023 | Mar 11, 2025 | CONSTRUCTION OF MULTI-PURPOSE BUILDING, BARANGAY DOOS DEL SUR, HINDANG, LEYTE | Completed | ₱4.9M |
| 24IG0123 | Sep 12, 2024 | CONSTRUCTION OF ROAD LEADING TO BONTOC CAVE, BRGY. BONTOC, HINDANG, LEYTE | Completed | ₱9.6M |
| 24IG0105 | Jul 29, 2024 | RAINWATER COLLECTORS IN PUBLIC FACILITIES | Completed | ₱2.9M |
Contract amounts as DPWH lists them, not payments. A contract alone does not establish irregularity.