FY2026 GAA: ₱6.79T
PisoScan

Project 19IG0093

DPWH infrastructure contract
Contract ID:
19IG0093
Fingerprint:
7ee935cbb0a90d…0a86e0e861 Verified
Status:
Completed
Physical progress:
100%
Timeline:
Start Oct 6, 2019 (7 yrs 1 mo ago) · Target/actual end Jan 3, 2020
Description:
CONSTRUCTION OF MULTI-PURPOSE BUILDING, BATO, LEYTE
Category:
Buildings and Facilities
Implementing office:
DPWH Leyte 5th DEO · Region VIII
Contractor:
CIRCLE Z VENTURES AND DEVELOPMENT CORP. · DPWH contractor code 36765
As listed: CIRCLE Z VENTURES & DEVELOPMENT CORP.
Contract amount:
₱5,221,755.00 (₱5.2M)
Funding source:
Regular Infra - GAA 2019 LP
Budget year:
2019

Matching PhilGEPS award entries (same contractor, same contract ID)

RecordDateProcuring entityAmount
87304f0938e3…Sep 16, 2019DEPARTMENT OF PUBLIC WORKS AND HIGHWAYS - LEYTE 5TH ED₱5,221,755.00

Other DPWH contracts in the same city / municipality

View all
ContractStartDescriptionStatusAmount
26IG0019Jul 27, 2026CONSTRUCTION OF BY-PASS AND DIVERSION ROADS - BATO BY-PASS ROAD, STA. 2+233 - 2+513, BARANGAY TABUNOK, LEYTEOn-Going₱33.0M
25IG0010Jun 3, 2025CONSTRUCTION OF ROAD, SITIO KAMANGGAHAN, BARANGAY BAGO, BATO, LEYTECompleted₱4.9M
25IG0065Jun 3, 2025NETWORK DEVELOPMENT - ROAD WIDENING - SECONDARY ROADS - BATO-BONTOC RD - K1117 + 879 - K1120+000On-Going₱77.2M
25IG0040May 20, 2025CONSTRUCTION OF MULTI-PURPOSE BUILDING, BARANGAY TABUNOK, BATO, LEYTECompleted₱4.9M
25IG0055May 20, 2025CONSTRUCTION (COMPLETION) OF MULTI-PURPOSE BUILDING, BARANGAY ANAHAWAN, BATO, LEYTECompleted₱3.0M
25IG0063May 20, 2025CONSTRUCTION OF MULTI-PURPOSE BUILDING, BARANGAY KALANGGAMAN, BATO, LEYTECompleted₱4.9M
25IG0016Mar 27, 2025NETWORK DEVELOPMENT - CONSTRUCTION OF BY-PASS AND DIVERSION ROADS - BATO BY-PASS ROAD, LEYTECompleted₱19.6M
25IG0014Mar 11, 2025CONSTRUCTION OF ROAD, BARANGAY TAGAYTAY, BATO, LEYTECompleted₱4.9M

Contract amounts as DPWH lists them, not payments. A contract alone does not establish irregularity.