Project 19IH0083
DPWH infrastructure contract
Contract ID:
19IH0083
Fingerprint:
3ca534fcc3290c…9119697d96 Verified
Status:
Completed
Physical progress:
100%
Timeline:
Start Oct 11, 2019 (7 yrs 1 mo ago) · Target/actual end Dec 9, 2019
Description:
REPAIR/IMPROVEMENT OF MULTI-PURPOSE BUILDING, BRGY. 3, CAPUL, N. SAMAR
Category:
Buildings and Facilities
Implementing office:
DPWH Northern Samar 1st DEO · Region VIII
Contractor:
CHRISTFER CONSTRUCTION & SUPPLY · DPWH contractor code 36029
Contract amount:
₱1,960,145.57 (₱2.0M)
Funding source:
Regular Infra - GAA 2019 LP
Budget year:
2019
Matching PhilGEPS award entries (same contractor, same contract ID)
| Record | Date | Procuring entity | Amount |
|---|---|---|---|
| adac0b6a7402… | Sep 27, 2019 | DEPARTMENT OF PUBLIC WORKS AND HIGHWAYS - NORTHERN SAMAR 1ST | ₱1,960,145.57 |
Other DPWH contracts in the same city / municipality
View all| Contract | Start | Description | Status | Amount |
|---|---|---|---|---|
| 25IH0088 | Sep 17, 2025 | CONSTRUCTION OF MULTIPURPOSE BUILDING, CAPUL NORTHERN SAMAR | On-Going | ₱6.9M |
| 25IH0012 | Sep 10, 2025 | CONSTRUCTION/IMPROVEMENT OF CAPUL CIRCUMFERENTIAL ROAD, AGUIN-LANDUSAN-SAWANG- SAGAOSAWAN-JUBANG-OSON-POBLACION SECTION, CAPUL, NORTHERN SAMAR | On-Going | ₱9.8M |
| 24I00351 | Dec 11, 2024 | CONSTRUCTION OF NEW SUPER HEALTH CENTERS/RHU - CAPUL SUPER HEALTH CENTER, NORTHERN SAMAR, CAPUL, NORTHERN SAMAR | On-Going | ₱11.9M |
| 24IH0079 | Aug 7, 2024 | CONCRETING OF SITIO PAL-OG, BRGY. POBLACION 5 TO BRGY. SAWANG FMR, BRGY. POBLACION 5 AND BRGY. SAWANG, CAPUL, NORTHERN SAMAR | On-Going | ₱19.7M |
| 24IH0044 | Apr 25, 2024 | CONSTRUCTION/IMPROVEMENT OF CAPUL CIRCUMFERENTIAL ROAD, AGUIN - LANDUSAN - SAWANG - SAGAOSAWAN - JUBANG - OSON - POBLACION SECTION, CAPUL, NORTHERN SAMAR | On-Going | ₱14.7M |
| 24IH0020 | Feb 22, 2024 | CONSTRUCTION OF ROAD, PHASE I, BARANGAY POBLACION 5 TO BARANGAY SAWANG, CAPUL, NORTHERN SAMAR | On-Going | ₱11.9M |
| 23IH0153 | Nov 22, 2023 | CONSTRUCTION OF 1STY3CL, OSON ES, CAPUL, NORTHERN SAMAR | Completed | ₱10.3M |
| 23IH0150 | Oct 26, 2023 | CONSTRUCTION OF SOLAR WATER SYSTEM, CAPUL, NORTHERN SAMAR | Completed | ₱9.8M |
Contract amounts as DPWH lists them, not payments. A contract alone does not establish irregularity.