Skip to content
FY2026 GAA: ₱6.79T
PisoScan

Project 19IK0062

DPWH infrastructure contract
Contract ID:
19IK0062
Fingerprint:
412fad37096121…b2d0d0bac4 Verified
Status:
Completed
Physical progress:
100%
Timeline:
Start Oct 14, 2019 (7 yrs 1 mo ago) · Target/actual end Apr 18, 2020
Description:
CONST. OF MODIFIED DESIGN WITH PARAPET, 1-STOREY, 2-CL SCHOOL BUILDING, TABAY E/S, HINABANGAN, SAMAR
Category:
Buildings and Facilities
Implementing office:
DPWH Samar 2nd DEO · Region VIII
Contractor:
HAL CONSTRUCTION · DPWH contractor code 46193
Contract amount:
₱4,363,023.16 (₱4.4M)
Funding source:
Outside Infra - GAA 2019 DepEd BEFF
Budget year:
2019

Matching PhilGEPS award entries (same contractor, same contract ID)

RecordDateProcuring entityAmount
122f2f0ef08e…Oct 4, 2019DEPARTMENT OF PUBLIC WORKS AND HIGHWAYS - SAMAR 2ND DEO₱4,363,023.16

Other DPWH contracts in the same city / municipality

View all
ContractStartDescriptionStatusAmount
25IK0047Jun 19, 2025CSSP- SIPAG- INTERJURISDICTIONALROADS AND/OR BRIDGES (ROADS THAT TRAVERSE MULTIPLE LGU JURISDICTION) CONST. OF ROAD, BRGY. BAGACAY TO BRGY. CONCORD, HINABANGAN, SAMAROn-Going₱29.4M
25IK0014Jun 3, 2025CSSP-SIPAG- INTERJURISDICTIONAL ROADS AND/OR BRIDGES (ROADS THAT TRAVERSE MULTIPLE LGU JURISDICTIONS), CONSTRUCTION OF ROAD, BARANGAY YABON TO BARANGAY CABALAGNAN, HINABANGAN, SAMAR, BARANGAY YABON TO BARANGAY CABALAGNAN, HINABANGAN, SAMAROn-Going₱29.4M
25I00039Apr 10, 2025ASSET PRESERVATION - REHABILITATION//RECONSTRUCTION/UPGRADING OF DAMAGED PAVED ROADS - PRIMARY ROADS - MAHARLIKA HIGHWAY (SN ISIDRO - SN JUANICO BR) - K0833+560 - K0833+900, K0834+299 - K0834+460, K0839+000 - K0839+786, K0840+200 - K0840+300, K0851+740 -On-Going₱58.1M
25IB0024Mar 27, 2025CONSTRUCTION/UPGRADING/REHABILITATION OF DRAINAGE ALONG NATIONAL ROADS, SECONDARY ROADS, WRIGHT-TAFT-BORONGAN ROAD, K0861+327 - K0861+382, K0861+406 - K0861+496, K0861+507 - K0861+940, K0861+970 - K0862+178, K0889+692 - K0889+825Completed₱7.8M
24IB0034Mar 11, 2024REHABILITATION/RECONSTRUCTION OF ROADS WITH SLIPS, SLOPE COLLAPSE AND LANDSLIDE SECONDARY ROADS, WRIGHT-TAFT-BORONGAN RD K0861+055-K0861+090Completed₱4.9M
24IK0028Feb 23, 2024ASSET PRESERVATION- REHAB./RECONST. OF ROADS WITH SLIPS, SLOPE COLLAPSE AND LANDSLIDE- SECONDARY ROADS- WRIGHT-TAFT-BORONGAN ROAD- K0852+100-K0852+121, HINABANGAN, SAMAROn-Going₱48.3M
24IK0029Feb 23, 2024NETWORK DEVELOPMENT- ROAD WIDENING- TERTIARY ROADS- HINABANGAN DIVERSION RD- K0837+(-075)-K0837+(-010), K0837+120-K0837+244Completed₱6.4M
23IK0110Dec 27, 2023NETWORK DEVELOPMENT PROGRAM- ROAD WIDENING- SECONDARY ROADS, WRIGHT-TAFT BORONGAN RD. (S00123SM)- K0828+(-409)- K0830+861 (2-4 LANES)On-Going₱191.0M

Contract amounts as DPWH lists them, not payments. A contract alone does not establish irregularity.