Skip to content
FY2026 GAA: ₱6.79T
PisoScan

Project 19JC0071

DPWH infrastructure contract
Contract ID:
19JC0071
Fingerprint:
9cda166fe3954e…27781f7000 Verified
Status:
Completed
Physical progress:
100%
Timeline:
Start Sep 26, 2019 (7 yrs 1 mo ago) · Target/actual end Jan 7, 2020
Description:
CONCRETING OF BRGY. MALAYAL-SITIO GUIMBA-SITIO PARANG FMR, BRGY. MALAYAL, SIBUCO, ZAMBOANGA DEL NORTE
Category:
Roads
Implementing office:
Contractor:
ST. JOSEPH CONSTRUCTION AND TRADING · DPWH contractor code 36890
Contract amount:
₱9,949,986.65 (₱9.9M)
Funding source:
Outside Infra - GAA 2019 DA FMR
Budget year:
2019

Matching PhilGEPS award entries (same contractor, same contract ID)

RecordDateProcuring entityAmount
ad61d6450ef5…Sep 2, 2019DEPARTMENT OF PUBLIC WORKS AND HIGHWAYS - ZAMBOANGA DEL NORT₱9,750,961.01

Other DPWH contracts in the same city / municipality

View all
ContractStartDescriptionStatusAmount
25JJ0001Mar 27, 2025PREVENTIVE MAINTENANCE - SECONDARY ROADS, ZAMBOANGA WEST COASTAL RD (SIBUCO-LIMPAPA SECTION) - (S01152MN) CHAINAGE 5761 - CHAINAGE 9030On-Going₱55.3M
25JJ0003Mar 27, 2025REHABILITATION/ RECONSTRUCTION/ UPGRADING OF DAMAGED PAVED ROADS - SECONDARY ROADS, ZAMBOANGA WEST COASTAL RD (SIBUCO-LIMPAPA SECTION) - CHAINAGE 13301 - CHAINAGE 13521Completed₱5.0M
25JJ0005Mar 27, 2025REHABILITATION/ RECONSTRUCTION OF ROADS WITH SLIPS, SLOPE COLLAPSE, AND LANDSLIDE - SECONDARY ROADS, SIOCON-SIRAWAI-SIBUCO-LIMPAPA RD - K2120 + 179 - K2120 + 311, K2120 + 364 - K2120 + 409Completed₱53.9M
25JJ0006Mar 27, 2025REHABILITATION/ RECONSTRUCTION OF ROADS WITH SLIPS, SLOPE COLLAPSE, AND LANDSLIDE - SECONDARY ROADS, SIOCON-SIRAWAI-SIBUCO-LIMPAPA RD - K2112 + 440 - K2112 + 500, K2119 + 149 - K2119 + 192, K2120 + 075 - K2120 + 105Completed₱15.4M
25JJ0007Mar 27, 2025REHABILITATION/ RECONSTRUCTION OF ROADS WITH SLIPS, SLOPE COLLAPSE, AND LANDSLIDE - SECONDARY ROADS, SIOCON-SIRAWAI-SIBUCO-LIMPAPA RD - K2122 + 600 - K2122 + 635, K2123 + 140 - K2123 + 156Completed₱10.3M
25JJ0011Mar 27, 2025REHABILITATION/ RECONSTRUCTION OF ROADS WITH SLIPS, SLOPE COLLAPSE, AND LANDSLIDE - SECONDARY ROADS, SIOCON-SIRAWAI-SIBUCO-LIMPAPA RD - K2135 + 871 - K2135 + 907, K2136 + 316 - K2136 + 358On-Going₱34.7M
25JJ0012Mar 27, 2025REHABILITATION/ RECONSTRUCTION OF ROADS WITH SLIPS, SLOPE COLLAPSE, AND LANDSLIDE - SECONDARY ROADS, SIOCON-SIRAWAI-SIBUCO-LIMPAPA RD - K2140 + 301 - K2140 + 334, K2143 + 326 -K2143 + 352, K2143 + 478 - K2143 + 518Completed₱23.8M
25JJ0013Mar 27, 2025REHABILITATION/ RECONSTRUCTION OF ROADS WITH SLIPS, SLOPE COLLAPSE, AND LANDSLIDE - SECONDARY ROADS, SIOCON-SIRAWAI-SIBUCO-LIMPAPA RD - K2144 + 033 - K2144 + 091, K2144 + 728 - K2144 + 752, K2144 + 902 - K2144 + 942Completed₱34.5M

Contract amounts as DPWH lists them, not payments. A contract alone does not establish irregularity.