Project 19K00084
DPWH infrastructure contract
Contract ID:
19K00084
Fingerprint:
6ea5b40d1e8663…bf1bdb760f Verified
Status:
Completed
Physical progress:
100%
Timeline:
Start Jul 26, 2019 (7 yrs 3 mo ago) · Target/actual end Apr 20, 2020
Description:
ROAD WIDENING, MARAMAG-MARADUGAO ROAD, K1592+402 - K1597+588, BUKIDNON
Category:
Roads
Implementing office:
DPWH Region X · Region X
Contractor:
C'ZARLES CONSTRUCTION & SUPPLY · DPWH contractor code 23426
Contract amount:
₱138,232,758.51 (₱138.2M)
Funding source:
Regular Infra - GAA 2019 OO-1
Budget year:
2019
Other DPWH contracts in the same city / municipality
View all| Contract | Start | Description | Status | Amount |
|---|---|---|---|---|
| 25KN0064 | Feb 16, 2026 | CONSTRUCTION OF CLASSROOMS, PASAYANON ES, KALILANGAN, BUKIDNON | On-Going | ₱2.9M |
| 25KN0065 | Feb 16, 2026 | CONSTRUCTION OF SCHOOL HEALTH FACILITIES, KALILANGAN CES, KALILANGAN, BUKIDNON | Completed | ₱2.9M |
| 25K00426 | Jul 11, 2025 | CONSTRUCTION OF ONE (1) UNIT 4-STOREY 12 DOORS QUARTERING FACILITY FOR OFFICER'S QUARTERS | On-Going | ₱111.3M |
| 25K00427 | Jul 11, 2025 | CONSTRUCTION OF ONE (1) UNIT 4-STOREY 12 DOORS QUARTERING FACILITY FOR ENLISTED PERSONNEL | On-Going | ₱85.7M |
| 25K00243 | May 30, 2025 | PREVENTIVE MAINTENANCE-SECONDARY RODS, BUKIDNON BDRY-NORTH COTABATO RD (S01606MN) - CHAINAGE 0 - CHAINAGE 10000 | On-Going | ₱235.4M |
| 25KN0052 | May 23, 2025 | CONCRETING OF SITIO DARUSALAM, BRGY. NINOY AQUINO FMR, BRGY. NINOY AQUINO, KALILANGAN, BUKIDNON | On-Going | ₱14.6M |
| 25KN0009 | Mar 26, 2025 | CONSTRUCTION OF MULTI-PURPOSE BUILDING, BARANGAY BARORAWON, KALILANGAN, BUKIDNON | On-Going | ₱12.9M |
| 25KN0042 | Mar 25, 2025 | CONSTRUCTION OF MULTI-PURPOSE BUILDING, BARANGAY BANGBANG, KALILANGAN, BUKIDNON | On-Going | ₱12.6M |
Contract amounts as DPWH lists them, not payments. A contract alone does not establish irregularity.