Project 19K00409
DPWH infrastructure contract
Contract ID:
19K00409
Fingerprint:
4aeaf6f0e9ca17…7972d51ce2 Verified
Status:
Completed
Physical progress:
100%
Timeline:
Start Dec 27, 2019 (6 yrs 10 mo ago) · Target/actual end Sep 13, 2020
Description:
CLUSTER 'F' CONSTRUCTION (COMPLETION) OF VARIOUS BRIDGES IN LANAO DEL SUR
Category:
GAA 2019 LP
Implementing office:
DPWH Region X · Region X
Contractor:
CDH CONSTRUCTION (37936) / M.M.A. ACHIEVER CONSTRUCTION & DEVELOPMENT CORP. · DPWH contractor code 32195
Contract amount:
₱118,218,922.68 (₱118.2M)
Funding source:
Regular Infra - GAA 2019 LP
Budget year:
2019
Other DPWH contracts in the same city / municipality
View all| Contract | Start | Description | Status | Amount |
|---|---|---|---|---|
| 24K00424 | Feb 5, 2025 | CONST.(COMPLETION) OF MULTI-PURPOSE BUILDING, BRGY BALINTAO, MAGUING, LANAO DEL SUR | On-Going | ₱1.8M |
| 24K00340 | Sep 26, 2024 | CONSTRUCTION OF MULTI-PURPOSE BUILDING, BRGY. BATO-BATO, MAGUING, LANAO DEL SUR | On-Going | ₱9.8M |
| 24K00423 | Sep 12, 2024 | REHAB./RECONST.OF ROADS WITH SLIPS, SLOPE COLLAPSE, AND LANDSLIDE-TERTIARY ROADS- MULONDO-WAO RD - (S01604MN) CHAINAGE 8600 - CHAINAGE 8800 | Completed | ₱28.7M |
| 24K00398 | Aug 12, 2024 | CONSTRUCTION OF MULTI-PURPOSE BUILDING, BRGY. BUTOD, MAGUING, LANAO DEL SUR | Completed | ₱7.4M |
| 24K00439 | Aug 12, 2024 | CONSTRUCTION OF MULTI-PURPOSE BUILDING, BRGY. BUBONG, MAGUING, LANAO DEL SUR | Completed | ₱7.1M |
| 24K00277 | Jun 17, 2024 | CONST./UPGRADING/REHABILITATION OF DRAINAGE ALONG NATIONAL ROADS-TERTIARY ROADS MULONDO-WAO ROAD, MAGUING, LANAO DEL SUR | On-Going | ₱25.2M |
| 24K00024 | May 23, 2024 | PAVING OF UNPAVED ROADS-TERTIARY ROADS, MULONDO-WAO ROAD-(S01604MN) CHAINAGE 19436-CHAINAGE 20307 | Completed | ₱47.3M |
| 24K00155 | May 3, 2024 | CONCRETING 1KM BRGY. ROAD PUROK 5-6, BRGY. FRANCFORT, AMAI MANABILANG, LANAO DEL SUR | Completed | ₱19.6M |
Contract amounts as DPWH lists them, not payments. A contract alone does not establish irregularity.