FY2026 GAA: ₱6.79T
PisoScan

Project 19KJ0194

DPWH infrastructure contract
Contract ID:
19KJ0194
Fingerprint:
1464169c345bc5…ab2822ea7f Verified
Status:
Completed
Physical progress:
100%
Timeline:
Start Oct 7, 2019 (7 yrs 1 mo ago) · Target/actual end Mar 4, 2020
Description:
CONSTRUCTION OF CLASSROOMS (BATCH1) 2STY4CL, TINACLAAN ES, CLARIN, MISAMIS OCCIDENTAL
Category:
Buildings and Facilities
Implementing office:
Contractor:
GRACE CONSTRUCTION CORPORATION · DPWH contractor code 3771
Contract amount:
₱18,997,587.00 (₱19.0M)
Funding source:
Outside Infra - GAA 2019 DepEd BEFF
Budget year:
2019

Matching PhilGEPS award entries (same contractor, same contract ID)

RecordDateProcuring entityAmount
f15fb9c42d88…Sep 23, 2019DEPARTMENT OF PUBLIC WORKS AND HIGHWAYS - MIS. OCC. SUB-DEO₱18,997,587.00

Other DPWH contracts in the same city / municipality

View all
ContractStartDescriptionStatusAmount
25KJ0118Oct 16, 2025CONSTRUCTION OF MULTI-PURPOSE BUILDINGS, CLARIN CLUSTER, CLARIN, MISAMIS OCCIDENTALOn-Going₱12.1M
25KJ0076Jul 23, 2025CONSTRUCTION OF BY-PASS AND DIVERSION ROADS MOUNTAIN BYPASS ROAD (PAN-AY - MIALEN SECTION), CLARIN, MISAMIS OCCIDENTALCompleted₱9.6M
25KJ0112Jul 23, 2025REHABILITATION OF EXISTING WATER SUPPLY SYSTEM, CLARIN, MISAMIS OCCIDENTALOn-Going₱9.7M
25KJ0040Jul 21, 2025CONSTRUCTION OF BY-PASS AND DIVERSION ROADS MOUNTAIN BYPASS ROAD (PAN-AY DIOT SECTION), CLARIN, MISAMIS OCCIDENTALOn-Going₱19.4M
25KJ0019Jul 9, 2025ACCESS ROADS AND/OR BRIDGES FROM THE NATIONAL ROADS LEADING TO MAJOR/STRATEGIC PUBLIC BUILDINGS/FACILITIES, CONSTRUCTION OF ROAD PUROK 5-PUROK 6, MONTOL DETACHMENT TO SITIO TIPAN ROAD, BGRY. STIMSON ABORDO. OZAMIZ CITYCompleted₱9.6M
25KJ0051Jul 9, 2025CONSTRUCTION/COMPLETION OF MULTI-PURPOSE BUILDING (BARANGAY HEALTH STATION), BRGY. KINANGAY SUR, CLARIN, MISAMIS OCCIDENTALCompleted₱2.4M
25KJ0052Jul 9, 2025CONSTRUCTION/COMPLETION OF MULTI-PURPOSE BUILDING (BARANGAY HEALTH STATION), BRGY. DUANGUICAN, TUDELA, MISAMIS OCCIDENTALCompleted₱2.4M
25KJ0088Jun 9, 2025CONCRETING OF PAN-AY TO MIALEN FMR, CLARIN, MISAMIS OCCIDENTALCompleted₱16.7M

Contract amounts as DPWH lists them, not payments. A contract alone does not establish irregularity.