Skip to content
FY2026 GAA: ₱6.79T
PisoScan

Project 19MA0107

DPWH infrastructure contract
Contract ID:
19MA0107
Fingerprint:
65c29156e77836…07119ba42c Verified
Status:
Completed
Physical progress:
100%
Timeline:
Start Nov 25, 2019 (6 yrs 11 mo ago) · Target/actual end Dec 26, 2019
Description:
CONCRETING OF BRGY. TONGGOL-BRGY. KULASI FMR, BRGY. TONGOL AND BRGY. KULASI, GENERAL S.K. PENDATUN, MAGUINDANAO
Category:
Roads
Implementing office:
Contractor:
TRIPLE S CONSTRUCTION · DPWH contractor code 44986
Contract amount:
₱4,973,982.23 (₱5.0M)
Funding source:
Outside Infra - GAA 2019 DA FMR
Budget year:
2019

Matching PhilGEPS award entries (same contractor, same contract ID)

RecordDateProcuring entityAmount
89c22e02a1f0…Nov 19, 2019DEPARTMENT OF PUBLIC WORKS AND HIGHWAYS - REGION XII - COTAB₱4,973,982.23

Other DPWH contracts in the same city / municipality

View all
ContractStartDescriptionStatusAmount
24M00269Dec 12, 2024CONSTRUCTION OF MULTI-PURPOSE FACILITY AT BARANGAY LAO LAO, GEN. SALIPADA K. PENDATUN, MAGUINDANAO DEL SUROn-Going₱6.8M
23M00227Nov 13, 2023CONSTRUCTION OF MULTI-PURPOSE BUILDING (COVERED COURT WITH STAGE AND BLEACHERS) IN BARANGAY MIDPANDACAN, GEN. S. K. PENDATUN, MAGUINDANAOOn-Going₱4.9M
23M00192Aug 30, 2023CONSTRUCTION OF SOLAR WATER SYSTEM, GEN. SALIPADA K. PENDATUN, MAGUINDANAOCompleted₱9.5M
23M00125Jun 23, 2023CONSTRUCTION OF MULTI-PURPOSE BUILDING (TRAINING CENTER) IN BARANGAY BADAK, GEN. SALIPADA K. PENDATUN, MAGUINDANAOCompleted₱6.8M
23M00146Apr 5, 2023CONSTRUCTION OF MULTI-PURPOSE BUILDING (PUBLIC MARKET), GENERAL S.K. PENDATUN, MAGUINDANAOOn-Going₱9.7M
22M00126Aug 15, 2022CONSTRUCTION OF MULTI-PURPOSE BUILDING (LEGISLATIVE BUILDING) IN GEN. SALIPADA K. PENDATUN, MAGUINDANAOCompleted₱6.7M
21MA0032Sep 2, 2021CONSTRUCTION OF MULTI-PURPOSE BUILDING, BARANGAY POBLACION, GEN. SK PENDATUN, MAGUINDANAOCompleted₱1.7M
20MA0067Oct 22, 2020CONSTRUCTION OF COVERED COURT, BRGY. QUIPOLOT, GEN. SALIPADA K. PENDATUN, MAGUINDANAOCompleted₱2.9M

Contract amounts as DPWH lists them, not payments. A contract alone does not establish irregularity.