FY2026 GAA: ₱6.79T
PisoScan

Project 19MF0061

DPWH infrastructure contract
Contract ID:
19MF0061
Fingerprint:
05387da79eefe3…8fb9093bd6 Verified
Status:
Completed
Physical progress:
100%
Timeline:
Start Oct 22, 2019 (7 yrs ago) · Target/actual end Feb 25, 2020
Description:
CONCRETING OF BRGY. TINAUNGAN FARM TO MARKET ROAD, STA. 0+000 - STA. 0+310, BRGY. TINAUNGAN, PRES. QUIRINO, SULTAN KUDARAT.
Category:
Roads
Implementing office:
Contractor:
ALPXR CONST. & BLDRS. CORP. · DPWH contractor code 44667
As listed: ALPXR CONST. & BLDRS. CORP
Contract amount:
₱4,846,573.55 (₱4.8M)
Funding source:
Outside Infra - GAA 2019 DA FMR
Budget year:
2019

Matching PhilGEPS award entries (same contractor, same contract ID)

RecordDateProcuring entityAmount
a0e3fe4baecd…Oct 1, 2019DEPARTMENT OF PUBLIC WORKS AND HIGHWAYS - SULTAN KUDARAT DEO₱4,846,573.55

Other DPWH contracts in the same city / municipality

View all
ContractStartDescriptionStatusAmount
25MG0020Apr 11, 2025ROAD WIDENING-MIDSAYAP-MARBEL RD-K1774+083-K1774+581Completed₱9.6M
25MF0031Mar 26, 2025CONSTRUCTION (COMPLETION) OF MULTI-PURPOSE BUILDING (BARANGAY HALL), BARANGAY BANNAWAG, PRESIDENT QUIRINO, SULTAN KUDARATCompleted₱3.0M
25MF0032Mar 26, 2025CONSTRUCTION (COMPLETION) OF MULTI-PURPOSE BUILDING (MINI GYM BLEACHERS), BARANGAY BANNAWAG, PRESIDENT QUIRINO, SULTAN KUDARATCompleted₱3.0M
25MG0002Feb 28, 2025PREVENTIVE MAINTENANCE OF ROAD: ASPHALT OVERLAY-MIDSAYAP-MARBEL RD-K1774+083-K1774+336, SOUH COTABATOCompleted₱11.2M
25MG0003Feb 28, 2025PREVENTIVE MAINTENANCE OF ROAD: ASPHALT OVERLAY-MIDSAYAP-MARBEL RD-K1775+000-K1775+570, SOUTH COTABATOCompleted₱38.0M
24M00200Jul 29, 2024CONSTRUCTION OF MULTI-PURPOSE BUILDING, BARANGAY POBLACION, PRESIDENT QUIRINO, SULTAN KUDARATCompleted₱9.9M
24MF0052May 15, 2024CONSTRUCTION OF 1-STOREY 2-CLASSROOM SCHOOL BUILDING IN PRESIDENT QUIRINO NATIONAL HIGH SCHOOL, BARANGAY POBLACION, PRESIDENT QUIRINO, SULTAN KUDARATCompleted₱5.0M
24MG0050May 15, 2024CONSTRUCTION OF MULTI-PURPOSE BUILDING, BRGY. NEW CUYAPO, TANTANGAN, SOUTH COTABATOCompleted₱4.9M

Contract amounts as DPWH lists them, not payments. A contract alone does not establish irregularity.