Project 19NA0072
DPWH infrastructure contract
Contract ID:
19NA0072
Fingerprint:
c295dcfc7e4927…009a4adf22 Verified
Status:
Completed
Physical progress:
100%
Timeline:
Start Dec 1, 2019 (6 yrs 11 mo ago) · Target/actual end Mar 24, 2020
Description:
CONSTRUCTION OF 1 UNIT 1 STY 3 CL WITH TOILET ATTACHED AND HANDWASHING FACILITY AT PUPOTSAN NHS (MAGALLANES NHS ANNEX), MAGALLANES, AGUSAN DEL NORTE
Category:
Buildings and Facilities
Implementing office:
DPWH Agusan del Norte DEO · Region XIII
Contractor:
Contract amount:
₱4,447,663.91 (₱4.4M)
Funding source:
Outside Infra - GAA 2019 DepEd BEFF
Budget year:
2019
Matching PhilGEPS award entries (same contractor, same contract ID)
| Record | Date | Procuring entity | Amount |
|---|---|---|---|
| 50fefc836f11… | Nov 15, 2019 | DEPARTMENT OF PUBLIC WORKS AND HIGHWAYS - AGUSAN DEL NORTE | ₱4,447,663.91 |
Other DPWH contracts in the same city / municipality
View all| Contract | Start | Description | Status | Amount |
|---|---|---|---|---|
| 25N00152 | May 19, 2025 | BANZA TO MAGALLANES ROAD LEADING TO CENTENNIAL TREE AND BEACHES, MAGALLANES, AGUSAN DEL NORTE | On-Going | ₱14.4M |
| 25NA0002 | Mar 24, 2025 | CONSTRUCTION OF ROAD ALONG SEAWALL DIKE FROM BARANGAY SANTO ROSARIO TO BARANGAY SANTO NINO, MAGALLANES, AGUSAN DEL NORTE | Completed | ₱9.9M |
| 25N00116 | Feb 21, 2025 | CONSTRUCTION OF FLOOD MITIGATION STRUCTURE AT LOWER AGUSAN RIVER, MAGALLANES PAGATPATAN SECTION, MAGALLANES, AGUSAN DEL NORTE | Completed | ₱286.0M |
| 25N00192 | Feb 21, 2025 | CONSTRUCTION OF SLOPE PROTECTION STRUCTURE PROTECTING ABUTMENT OF BANZA BRIDGE 3 ALONG BANZA-MAGALLANES ROAD, PACKAGE 2, AGUSAN DEL NORTE | Completed | ₱143.8M |
| 25NA0019 | Feb 13, 2025 | CONSTRUCTION OF MULTI-PURPOSE BUILDING (COVERED COURT), CALOC-AN ELEMENTARY SCHOOL, BARANGAY CALOC-AN, MAGALLANES, AGUSAN DEL NORTE | Completed | ₱4.9M |
| 24N00069 | Oct 17, 2024 | BANZA TO MAGALLANES ROAD LEADING TO CENTENNIAL TREE AND BEACHES, MAGALLANES, AGUSAN DEL NORTE | Completed | ₱147.2M |
| 24N00070 | Oct 17, 2024 | BANZA TO MAGALLANES ROAD LEADING TO CENTENNIAL TREE AND BEACHES, MAGALLANES, AGUSAN DEL NORTE, PACKAGE II | Completed | ₱96.5M |
| 24NA0011 | Feb 21, 2024 | CONSTRUCTION OF FLOOD CONTROL MITIGATION STRUCTURE , LA FORTUNA, BARANGAY BUHANG, MAGALLANES, AGUSAN DEL NORTE | Completed | ₱96.4M |
Contract amounts as DPWH lists them, not payments. A contract alone does not establish irregularity.