Skip to content
FY2026 GAA: ₱6.79T
PisoScan

Project 19O00026

DPWH infrastructure contract
Contract ID:
19O00026
Fingerprint:
eb699dfab805e6…05d101ed6e Verified
Status:
Completed
Physical progress:
100%
Timeline:
Start Sep 13, 2019 (7 yrs 2 mo ago) · Target/actual end Jul 19, 2021
Description:
CONSTRUCTION OF BRIDGE ALONG PARANAQUE RIVER ADJACENT TO PARANAQUE INTEGRATED TERMINAL EXCHANGE (PARANAQUE ITX) DON GALO, PARANAQUE CITY
Category:
Bridges
Implementing office:
DPWH National Capital Region · National Capital Region
Contractor:
J. H. PAJARA CONSTRUCTION CORPORATION · DPWH contractor code 1890
As listed: J.H. PAJARA CONSTRUCTION CORPORATION
Contract amount:
₱143,028,470.02 (₱143.0M)
Funding source:
Regular Infra - GAA 2019 LP
Budget year:
2019

Matching PhilGEPS award entries (same contractor, same contract ID)

RecordDateProcuring entityAmount
ade15ebc0a0b…Aug 30, 2019DEPARTMENT OF PUBLIC WORKS AND HIGHWAYS - NCR₱130,032,047.43

Other DPWH contracts in the same city / municipality

View all
ContractStartDescriptionStatusAmount
26OE0029Sep 2, 2026CONSTRUCTION (COMPLETION) OF TWO (2) STOREY MULTI-PURPOSE BUILDING (BARANGAY LEARNING CENTER - MADRASA SCHOOL), BRGY 648, SAN MIGUEL, MANILAOn-Going₱2.9M
26OE0039Sep 2, 2026CONSTRUCTION OF MULTI-PURPOSE BUILDING, BARANGAY 186, GAGALANGIN, TONDO, MANILA, 14.63227555, 120.97601666On-Going₱4.8M
26OE0040Sep 2, 2026CONSTRUCTION (COMPLETION) OF MULTI-PURPOSE BUILDING, BRGY. 186, GAGALANGIN TONDO, MANILAOn-Going₱2.9M
26OE0041Sep 2, 2026CONSTRUCTION OF LTO MANILA NORTH DISTRICT OFFICE, TAYUMAN STREET, STA. CRUZ, MANILAOn-Going₱48.0M
26OE0044Sep 2, 2026CONSTRUCTION OF MULTI-PURPOSE BUILDING AT BARANGAY 592 (PHASE II), MANILA CITY (14.60035581, 121.01283465)On-Going₱19.2M
26OE0022Aug 20, 2026REHABILITATION / MAJOR REPAIR OF PERMANENT BRIDGES - SUNOG-APOG BR. (B01792LZ) ALONG H LOPEZ BLVDOn-Going₱18.0M
26OE0026Jul 28, 2026REHABILITATION/ MAJOR REPAIR OF PERMANENT BRIDGES - C. PALANCA BR. (B02271LZ) ALONG C PALANCA ST, PHASE IIOn-Going₱12.7M
26OE0030Jul 28, 2026REHABILITATION/ MAJOR REPAIR OF PERMANENT BRIDGES - NAGTAHAN FLY-OVER (B03338LZ) ALONG NAGTAHAN BRIDGE / FLY-OVER (PHASE II)On-Going₱22.7M

Contract amounts as DPWH lists them, not payments. A contract alone does not establish irregularity.