Project 19OD0227

DPWH infrastructure contract
Contract ID:
19OD0227
Fingerprint:
668630f1d39847…c4420b29e5 Verified
Status:
Completed
Physical progress:
100%
Timeline:
Start Jun 27, 2019 (7 yrs 4 mo ago) · Target/actual end Oct 11, 2020
Description:
REHABILITATION/ RECONSTRUCTION/ UPGRADING OF DAMAGED PAVED ROADS-SECONDARY ROADS, C-3 ROAD - K0011+-035 - K0011+681
Category:
Roads
Implementing office:
DPWH Metro Manila 3rd DEO · National Capital Region
Contractor:
J. SIMEON CONSTRUCTION · DPWH contractor code 31867
Contract amount:
₱39,221,158.97 (₱39.2M)
Funding source:
Regular Infra - GAA 2019 OO-1
Budget year:
2019

Matching PhilGEPS award entries (same contractor, same contract ID)

RecordDateProcuring entityAmount
08979e5a3308…Jun 11, 2019DEPARTMENT OF PUBLIC WORKS AND HIGHWAYS - METRO MANILA 3RD E₱39,221,158.97

Other DPWH contracts in the same city / municipality

View all
ContractStartDescriptionStatusAmount
25OD0370Jul 28, 2025CONSTRUCTION OF MULTI-PURPOSE BUILDING, NORTH OLYMPUS, BARANGAY 172, CALOOCAN CITYOn-Going₱9.2M
25OD0371Jul 28, 2025CONSTRUCTION OF MULTI-PURPOSE BUILDING, BARANGAY 156, CALOOCAN CITYOn-Going₱10.5M
25OD0373Jul 28, 2025CONSTRUCTION (COMPLETION) OF MULTI-PURPOSE BUILDING (COVERED COURT), CELINA HOMES, BARANGAY 168, CALOOCAN CITYOn-Going₱4.8M
25OD0374Jul 28, 2025CONSTRUCTION OF MULTI-PURPOSE BUILDING (COVERED COURT), PHASE 2, BARANGAY 171, CALOOCAN CITYCompleted₱4.8M
25OD0375Jul 28, 2025CONSTRUCTION (COMPLETION) OF MULTI-PURPOSE BUILDING (SPORTS COMPLEX), BARANGAY 176, CALOOCAN CITY (PHASE 3)On-Going₱23.9M
25OD0376Jul 28, 2025CONSTRUCTION OF MULTI-PURPOSE BUILDING, BRGY. 180, CALOOCAN CITYOn-Going₱28.6M
25OD0368Jul 21, 2025CONSTRUCTION OF MULTI-PURPOSE BUILDING (COVERED COURT), BARANGAY 153, CALOOCAN CITYOn-Going₱28.7M
25OD0360Jul 9, 2025CONSTRUCTION (COMPLETION) PUP NORTH CALOOCAN CITY CAMPUS ACADEMIC BUILDING INCLUDING GROUND IMPROVEMENT (PHASE 6), BRGY. 168, CALOOCAN CITYOn-Going₱139.3M

Contract amounts as DPWH lists them, not payments. A contract alone does not establish irregularity.