Project 19OE0079

DPWH infrastructure contract
Contract ID:
19OE0079
Fingerprint:
f0564cacee4c3b…d1dd01c84f Verified
Status:
Completed
Physical progress:
100%
Timeline:
Start Jul 2, 2019 (7 yrs 4 mo ago) · Target/actual end Dec 28, 2019
Description:
LOCAL PROGRAM LOCAL INFRASTRUCTURE PROGRAM FLOOD CONTROL AND DRAINAGE DRAINAGE / PROTECTION WORKS CONCRETING / UPGRADING AND DRAINAGE IMPROVEMENT OF ROADS AND PATHWAYS, BRGY. 147 ZONE 13 TO BRGY. 267 ZONE 24, MANILA
Category:
Roads
Implementing office:
DPWH North Manila DEO · National Capital Region
Contractor:
THREE W BUILDERS, INC. · DPWH contractor code 10722
Contract amount:
₱9,553,449.04 (₱9.6M)
Funding source:
Regular Infra - GAA 2019 LP
Budget year:
2019

Matching PhilGEPS award entries (same contractor, same contract ID)

RecordDateProcuring entityAmount
3d056d4e44ca…Jun 19, 2019DEPARTMENT OF PUBLIC WORKS AND HIGHWAYS - NORTH METRO MANILA₱9,553,449.04

Other DPWH contracts in the same city / municipality

View all
ContractStartDescriptionStatusAmount
26OE0029Sep 2, 2026CONSTRUCTION (COMPLETION) OF TWO (2) STOREY MULTI-PURPOSE BUILDING (BARANGAY LEARNING CENTER - MADRASA SCHOOL), BRGY 648, SAN MIGUEL, MANILAOn-Going₱2.9M
26OE0039Sep 2, 2026CONSTRUCTION OF MULTI-PURPOSE BUILDING, BARANGAY 186, GAGALANGIN, TONDO, MANILA, 14.63227555, 120.97601666On-Going₱4.8M
26OE0040Sep 2, 2026CONSTRUCTION (COMPLETION) OF MULTI-PURPOSE BUILDING, BRGY. 186, GAGALANGIN TONDO, MANILAOn-Going₱2.9M
26OE0041Sep 2, 2026CONSTRUCTION OF LTO MANILA NORTH DISTRICT OFFICE, TAYUMAN STREET, STA. CRUZ, MANILAOn-Going₱48.0M
26OE0044Sep 2, 2026CONSTRUCTION OF MULTI-PURPOSE BUILDING AT BARANGAY 592 (PHASE II), MANILA CITY (14.60035581, 121.01283465)On-Going₱19.2M
26OE0022Aug 20, 2026REHABILITATION / MAJOR REPAIR OF PERMANENT BRIDGES - SUNOG-APOG BR. (B01792LZ) ALONG H LOPEZ BLVDOn-Going₱18.0M
26OE0026Jul 28, 2026REHABILITATION/ MAJOR REPAIR OF PERMANENT BRIDGES - C. PALANCA BR. (B02271LZ) ALONG C PALANCA ST, PHASE IIOn-Going₱12.7M
26OE0030Jul 28, 2026REHABILITATION/ MAJOR REPAIR OF PERMANENT BRIDGES - NAGTAHAN FLY-OVER (B03338LZ) ALONG NAGTAHAN BRIDGE / FLY-OVER (PHASE II)On-Going₱22.7M

Contract amounts as DPWH lists them, not payments. A contract alone does not establish irregularity.