Skip to content
FY2026 GAA: ₱6.79T
PisoScan

Project 19PE0034

DPWH infrastructure contract
Hashed input (canonical JSON of the source row)
["dpwh","19PE0034","CONSTRUCTION/ REHABILITATION OF FLOOD MITIGATION FACILITIES WITHIN MAJOR RIVER BASINS AND PRINCIPAL RIVERS: CONSTRUCTION FLOOD MITIGATION STRUCTURE ALONG BUED RIVER BASIN, DUNGON SECTION, TUBA, BENGUET","Flood Control and Drainage","Completed",48460534,0,100,"Benguet 1st DEO","Cordillera Administrative Region","RODEKOM GENERAL CONSTRUCTION AND ENTERPRISE (38656)","2019-06-17","2019-09-16",2019,"Regular Infra - GAA 2019 OO-2",16.23659,120.51699,"1401113000","1401100000"]
SHA-256
4abd269a5ed061258494da8f1826a4c1491fb40c38bbcb0ce286a402da9942e2