Project 20AC0023
DPWH infrastructure contract
Contract ID:
20AC0023
Fingerprint:
5cbd8a571a7b75…e75b673ec4 Verified
Status:
Completed
Physical progress:
100%
Timeline:
Start May 20, 2020 (6 yrs 5 mo ago) · Target/actual end Aug 3, 2020
Description:
CONSTRUCTION OF MULTI-PURPOSE BUILDING, BRGY. SIVED, STO. DOMINGO, ILOCOS SUR
Category:
Buildings and Facilities
Implementing office:
DPWH Ilocos Sur 1st DEO · Region I
Contractor:
739 BUILDERS · DPWH contractor code 31174
Contract amount:
₱2,475,000.00 (₱2.5M)
Funding source:
Regular Infra - GAA 2020 LP
Budget year:
2020
Matching PhilGEPS award entries (same contractor, same contract ID)
| Record | Date | Procuring entity | Amount |
|---|---|---|---|
| efdf31572ab4… | May 12, 2020 | DEPARTMENT OF PUBLIC WORKS AND HIGHWAYS - ILOCOS SUR 1ST DEO | ₱2,409,383.37 |
Other DPWH contracts in the same city / municipality
View all| Contract | Start | Description | Status | Amount |
|---|---|---|---|---|
| 25AC0044 | Jul 25, 2025 | COMPLETION OF MULTI-PURPOSE BUILDING (LEGISLATIVE BUILDING) STO. DOMINGO, ILOCOS SUR | On-Going | ₱39.4M |
| 25AC0002 | Jun 27, 2025 | PREVENTIVE MAINTENANCE - PRIMARY ROADS MANILA NORTH RD - K0413+134 - K0414+869 | Completed | ₱46.8M |
| 25AC0071 | Jun 11, 2025 | CONSTRUCTION OF ROAD, SANTO DOMINGO, ILOCOS SUR | Completed | ₱5.7M |
| 25AC0035 | Jun 9, 2025 | REPLACEMENT OF BRIDGE, KALIWET, SANTO DOMINGO, ILOCOS SUR | On-Going | ₱35.1M |
| 25A00224 | Feb 25, 2025 | CONSTRUCTION OF BY-PASS AND DIVERSION ROADS - VIGAN-CABUGAO COASTAL/DIVERSION ROAD, PACKAGE 1, ILOCOS SUR | Completed | ₱33.9M |
| 25A00211 | Feb 24, 2025 | CONSTRUCTION OF BY-PASS AND DIVERSION ROADS - VIGAN-CABUGAO COASTAL/DIVERSION ROAD, PACKAGE 2, ILOCOS SUR | On-Going | ₱29.5M |
| 25AC0014 | Feb 21, 2025 | CONSTRUCTION OF ROAD, BARANGAY CABIGBIGAAN AND PADU CHICO, SANTO DOMINGO, ILOCOS SUR | Completed | ₱19.1M |
| 25AC0022 | Feb 21, 2025 | CONSTRUCTION OF MULTI-PURPOSE BUILDING, BARANGAY SANTO TOMAS, SANTO DOMINGO, ILOCOS SUR | Completed | ₱4.8M |
Contract amounts as DPWH lists them, not payments. A contract alone does not establish irregularity.