FY2026 GAA: ₱6.79T
PisoScan

Project 20AF0047

DPWH infrastructure contract
Contract ID:
20AF0047
Fingerprint:
77c36d1842bdbb…90532f7244 Verified
Status:
Completed
Physical progress:
100%
Timeline:
Start Feb 24, 2020 (6 yrs 8 mo ago) · Target/actual end May 20, 2020
Description:
CONST.OF MULTI-PURPOSE BLDG,BRGY. STA RITA EAST ARINGAY,LA UNION
Category:
Buildings and Facilities
Implementing office:
Contractor:
E. E. MADAYAG CONSTRUCTION · DPWH contractor code 25029
As listed: E.E. MADAYAG CONSTRUCTION
Contract amount:
₱2,895,750.00 (₱2.9M)
Funding source:
Regular Infra - GAA 2020 LP
Budget year:
2020

Matching PhilGEPS award entries (same contractor, same contract ID)

RecordDateProcuring entityAmount
cedd4cf83e27…Feb 5, 2020DEPARTMENT OF PUBLIC WORKS AND HIGHWAYS - LA UNION 2ND ED₱2,895,750.00

Other DPWH contracts in the same city / municipality

View all
ContractStartDescriptionStatusAmount
25A00526Jun 16, 2025BASIC INFRASTRUCTURE PROGRAM (BIP), CONSTRUCTION OF FLOOD CONTROL STRUCTURE ALONG ARINGAY RIVER BASIN, BARANGAY SANTA CECILLA, ARINGAY, LA UNIONOn-Going₱67.2M
25AF0100Jun 11, 2025CONST/REHAB OF FLOOD MIT. FACI W/IN MAJOR RIVER BASINS & PRIN RIVERS - CONST. OF FLOOD MIT STRUCTURE ALONG ARINGAY RIVER BASIN, BRGY. POBLACION ARINGAY, LU (PHASE I)On-Going₱93.6M
25AF0101Jun 11, 2025CONST/REHAB OF FLOOD MIT. FACI W/IN MAJOR RIVER BASINS & PRINCIPAL RIVERS - CONST OF FLOOD MIT. STRUCTURE ALONG ARINGAY RIVER BASIN, BRGY. POBLACION ARINGAY, LU (PHASE 2)Completed₱93.6M
25AF0102Jun 11, 2025CONST/REHAB OF FLOOD MIT. FACI W/IN MAJOR RIVER BASINS & PRINCIPAL RIVERS - CONST. OF FLOOD MIT. STRUCTURE ALONG ARINGAY RIVER BASIN, BRGY. POBLACION, ARINGAY, LU (PHASE 3)Completed₱93.5M
25AF0103Jun 11, 2025CONST/REHAB. OF FLOOD MIT. FACI W/IN MAJOR RIVER BASINS & PRINCIPAL RIVERS - CONST. OF FLOOD MIT. STRUCTURE ALONG ARINGAY RIVER BASIN, BRGY. SAN JUAN WEST, ARINGAY, LA UNIONCompleted₱93.6M
25AF0104Jun 11, 2025CONST/REHAB OF FLOOD MIT. FACI W/IN MAJOR RIVER BASIN & PRINCIPAL RIVERS - CONST OF FOLOOD MIT. STRUCTURE ALONG ARINGAY, RIVER BASIN, BRGY. SAN SIMIN EAST, ARINGAY, LUOn-Going₱93.6M
25AF0105Jun 11, 2025CONST/REHAB OF FLOOD MIT FACI W/IN MAJOR RIVER BASINS & PRINCIPAL RIVERS - CONST. OF FLOOD MIT STRUCTURE ALONG ARINGAY RIVER BASIN, BRGY. SAN SIMON WEST, ARINGAY, LU (PHASE 1)On-Going₱93.6M
25AF0106Jun 11, 2025CONST/REHAB OF FLOOD MIT. FACI W/IN MAJOR RIVER BASINS & PRINCIPAL RIVERS - CONST. OF FLOOD MIT. STRUCTURE ALONG ARINGAY RIVER BASIN, BRGY. SAN SIMON WEST, ARINGAY, LU (PHASE 2)On-Going₱93.6M

Contract amounts as DPWH lists them, not payments. A contract alone does not establish irregularity.